File #: 2020-0695   
Type: Informational Report Status: Agenda Ready
File created: 10/5/2020 In control: Crenshaw Project Corporation
On agenda: 12/3/2020 Final action: 12/3/2020
Title: RECEIVE AND FILE status report on Crenshaw Project Corporation (CPC) Transportation Infrastructure and Innovation Act (TIFIA) Loan administration activities during the calendar year 2020.
Sponsors: Finance, Budget and Audit Committee
Indexes: Budgeting, Crenshaw/LAX Transit Corridor Project, Informational Report, Los Angeles International Airport, Metro Rail C Line, Metro Rail E Line, Metro Rail K Line, Project, Transportation Infrastructure Finance and Innovation Act of 1998
Attachments: 1. Attachment A - CrenshawLAX Project Funding Table
Meeting_Body
Crenshaw Project Corporation


One Gateway Plaza
Los Angeles, CA 90012

CRENSHAW PROJECT CORPORATION BOARD MEETING
DECEMBER 3, 2020

Subject
SUBJECT: TRANSPORTATION INFRASTRUCTURE FINANCE AND INNOVATION ACT (TIFIA) LOAN ADMINISTRATION ACTIVITIES

Action
ACTION: RECEIVE AND FILE

Heading
RECOMMENDATION

Title
RECEIVE AND FILE status report on Crenshaw Project Corporation (CPC) Transportation Infrastructure and Innovation Act (TIFIA) Loan administration activities during the calendar year 2020.

Issue
ISSUE

The Crenshaw Project Corporation was formed in 2012 to act as the TIFIA Loan conduit borrower and the Transportation Investment Generating Economic Recovery (TIGER) II TIFIA Payment grant sub-recipient for the Crenshaw/LAX Transit Corridor Project (Crenshaw/LAX).

This report provides an update to the Board about CPC administrative actions taken pursuant to the loan agreement since the last update at the CPC Meeting held December 5, 2019. As of August 25, 2016, the CPC had drawn all of the $545.9 million TIFIA Loan available to the Crenshaw/LAX Project. As of August 27, 2020, the TIFIA loan was paid off, in full.

Background
BACKGROUND

The Crenshaw Project Corporation (CPC) reports to the Board annually the loan administrative activities that have taken place during the current calendar year.

Discussion
DISCUSSION

Subsequent to the CPC Meeting held December 5, 2019 staff has completed the following actions in 2020 to administer the TIFIA Loan:

* Obtained annual credit rating;
* Paid the annual TIFIA Lender Loan Servicing Fee;
* Submitted to TIFIA:
o Reports and presentations material sent to rating agencies for rating on any indebtedness secured by Proposition A, Proposition C, and Measure R sales taxes and General Revenues;
o Preliminary Official Statements and Official Statements filed for all LACMTA bond issuances;
o Unaudited Quarterly Financial Statements of LACMTA and CPC;
o Audited Annual Financial Statements of CPC;
o LAC...