File #: 2020-0062   
Type: Contract Status: Passed
File created: 1/13/2020 In control: Board of Directors - Regular Board Meeting
On agenda: 5/27/2021 Final action: 5/27/2021
Title: AUTHORIZE the Chief Executive Officer to: A. NEGOTIATE AND EXECUTE a cost reimbursable Contract with SoCal Edison (SCE) to upgrade Division 9 (D9) and EL Monte Bus Depot utilities to support the full electrification of Battery Electric Buses procured from BYD, for an amount Not-To-Exceed $19,565,853. B. EXECUTE Modification No. 7 to BYD Coach & Bus, LLC (BYD), to add forty-four (44) Heliox Depot Chargers, software licenses, installation and commissioning support, and twelve (12) year warranty service and support for D9 charging infrastructure at the Firm Fixed price of $22,938,872 increasing the Contract Value from $48,528,900 to $71,467,772. C. INCREASE the Contract Modification Authority amount from $4,777,472 to $30,778,325 to incorporate upgrades to the charging infrastructure and for vehicle configuration changes for Contract OP28367-002, with BYD Coach & Bus, LLC. CONSIDER: D. FIND that awarding a design-build delivery method authority, pursuant to Public Utilities Code Sect...
Sponsors: Operations, Safety, and Customer Experience Commit
Indexes: Budgeting, Construction, Contractors, Contracts, Project
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification Log, 3. Attachment C- DEOD Summary, 4. Attachment D - Funding-Expenditure Plan, 5. Presentation
Meeting_Body
EXECUTIVE MANAGEMENT COMMITTEE
MAY 20, 2021

Subject
SUBJECT: EXECUTE CONTRACT WITH SOUTHERN CALIFORNIA EDISON (SCE) TO UPGRADE UTILITIES AT DIVISION 9 & EL MONTE TRANSIT CENTER, EXECUTE CONTRACT MODIFICATION WITH BYD FOR DIVISION 9 (D9) DEPOT CHARGERS, AND GRANT DESIGN-BUILD AUTHORITY FOR CHARGING INFRASTRUCTURE

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to:

A. NEGOTIATE AND EXECUTE a cost reimbursable Contract with SoCal Edison (SCE) to upgrade Division 9 (D9) and EL Monte Bus Depot utilities to support the full electrification of Battery Electric Buses procured from BYD, for an amount Not-To-Exceed $19,565,853.

B. EXECUTE Modification No. 7 to BYD Coach & Bus, LLC (BYD), to add forty-four (44) Heliox Depot Chargers, software licenses, installation and commissioning support, and twelve (12) year warranty service and support for D9 charging infrastructure at the Firm Fixed price of $22,938,872 increasing the Contract Value from $48,528,900 to $71,467,772.

C. INCREASE the Contract Modification Authority amount from $4,777,472 to $30,778,325 to incorporate upgrades to the charging infrastructure and for vehicle configuration changes for Contract OP28367-002, with BYD Coach & Bus, LLC.

CONSIDER:

D. FIND that awarding a design-build delivery method authority, pursuant to Public Utilities Code Section 130242(b), will achieve for Metro certain private sector efficiencies through the integration of design, project work and components.

Approval requires a two-thirds affirmative vote.

E. Approve the hiring of an initial five (5) new, non-contract full-time employees as part of the FY22 midyear budget process to ensure the successful delivery of the ZEB program.


Issue
ISSUE

In July 2017, Metro's Board of Directors approved a motion to "convert the Metro Orange Line to full Zero Emission operation by 2020 and the Metro Silver Line as soon as feasible, thereafter."
...

Click here for full text