Title: RECEIVE AND FILE status report on the Los Angeles Aerial Rapid Transit project.
Sponsors: Planning and Programming Committee
Indexes: Alignment, Budgeting, California Environmental Quality Act, Chinatown, Chinatown Station, Construction, Dodger Stadium, Environmental Impact Report, Housing, Intersections, Link Union Station, Los Angeles Union Station, Metro Equity Platform, Metro Rail A Line, Metro Rail L Line, Notice Of Preparation, Outreach, Program, Project, Strategic planning, Unsolicited Proposal Policy, Walking
Attachments: 1. Attachment A - Broadway Alignment with Station Locations, 2. Attachment B - Fare Letter to Metro from ARTT, 3. Attachment C - Community Outreach During NOP Scoping Period, 4. Presentation
Meeting_Body
EXECUTIVE MANAGEMENT COMMITTEE
JUNE 17, 2021

Subject
SUBJECT: LOS ANGELES AERIAL RAPID TRANSIT PROJECT UPDATE

Action
ACTION: RECEIVE AND FILE

Heading
RECOMMENDATION

Title
RECEIVE AND FILE status report on the Los Angeles Aerial Rapid Transit project.

Issue
ISSUE

This Board report updates the Board of Directors on the status of the Los Angeles Aerial Rapid Transit project ("Project"). Metro is serving as the California Environmental Quality Act (CEQA) lead agency for the Project, which is completely funded by Aerial Rapid Transit Technologies LLC (ARTT), including Metro staff time. Project status updates to the Board have been presented twice in the past two years, in April 2019 and September 2020.

Background
BACKGROUND

ARTT, a private company, submitted an Unsolicited Proposal to Metro in April 2018 to fund/finance, design, construct, operate, and maintain the Los Angeles Aerial Rapid Transit gondola connecting Union Station and Dodger Stadium. After reviewing the Phase 1 submittal, Metro requested a Phase II of ARTT's Unsolicited Proposal for the Project. In December 2018, Metro formally concluded the Unsolicited Proposal process and began exclusive negotiations with ARTT. The Memorandum of Agreement (MOA) between ARTT and Metro was executed in April 2019. In accordance with the MOA, Metro will act as the lead agency for the Project's environmental clearance.

CEQA lead agency as defined under CEQA is the public agency which has the principal responsibility for carrying out or approving a project which may have a significant effect upon the environment. Cities and counties are frequently CEQA lead agencies for real estate developments, but this is the first time Metro is serving as the CEQA lead agency for a privately initiated and funded project.

Discussion
DISCUSSION

Alignment
The Project would connect Union Station and the Dodger Stadium via an aerial gondola system. The Project will be generally located in the public ri...