File #: 2022-0016   
Type: Contract Status: Consent Calendar
File created: 1/11/2022 In control: Board of Directors - Regular Board Meeting
On agenda: 3/24/2022 Final action: 3/24/2022
Title: CONSIDER: A. AUTHORIZING the Chief Executive Officer to execute Modification No. 14 to Contract No. AE5999300 with WSP USA, Inc. to provide environmental technical work and outreach support to complete the Final Environmental Impact Statement/Environmental Impact Report (FEIS/FEIR), as well as conduct additional technical analysis to identify a cost-effective alignment route for the Slauson/A Line (Blue) to Los Angeles Union Station segment of the West Santa Ana Branch (WSAB) Transit Corridor Project in the amount of $13,601,672, increasing the Total Contract Value from $29,786,881 to $43,388,553 and to extend the Contract Period of Performance through June 30, 2023; and B. INCREASING Contract Modification Authority (CMA) specific to Contract No. AE5999300 in the amount of $1,000,000 from $2,476,120 to $3,476,120 to support additional environmental assessment work, and any other future technical work identified through future coordination efforts and/or as directed by the Board. HAH...
Sponsors: Planning and Programming Committee
Indexes: Alignment, Artesia, Board approved a Motion, Budgeting, Cerritos, Contracts, Environmental Impact Report, Environmental impact statements, Eric Garcetti, Federal Transit Administration, Fernando Dutra, Gateway Cities (Southeast LA County) Service Sector, Gateway Cities subregion, Hilda Solis, Holly J. Mitchell, Janice Hahn, Los Angeles Union Station, Metro Rail A Line, Motion / Motion Response, Outreach, Procurement, Project, West Santa Ana Branch Corridor - Administration (Project), West Santa Ana Branch Transit Corridor, West Santa Ana Branch Transit Corridor (WSAB) Project
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification Log, 3. Attachment C - DEOD Summary, 4. Presentation
Related files: 2022-0270
Meeting_Body
REVISED
PLANNING AND PROGRAMMING COMMITTEE
MARCH 16, 2022

Subject
SUBJECT: WEST SANTA ANA BRANCH TRANSIT CORRIDOR PROJECT

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
CONSIDER:

A. AUTHORIZING the Chief Executive Officer to execute Modification No. 14 to Contract No. AE5999300 with WSP USA, Inc. to provide environmental technical work and outreach support to complete the Final Environmental Impact Statement/Environmental Impact Report (FEIS/FEIR), as well as conduct additional technical analysis to identify a cost-effective alignment route for the Slauson/A Line (Blue) to Los Angeles Union Station segment of the West Santa Ana Branch (WSAB) Transit Corridor Project in the amount of $13,601,672, increasing the Total Contract Value from $29,786,881 to $43,388,553 and to extend the Contract Period of Performance through June 30, 2023; and

B. INCREASING Contract Modification Authority (CMA) specific to Contract No. AE5999300 in the amount of $1,000,000 from $2,476,120 to $3,476,120 to support additional environmental assessment work, and any other future technical work identified through future coordination efforts and/or as directed by the Board.

HAHN AMENDMENT:

The cities of Cerritos and Artesia have requested confirmation that Metro will be assessing the aerial segment at the intersection of 183rd and Gridley for this possibility of cut-and-cover, to see if that can be done at a lower cost.

In addition, Cerritos has requested evaluation of a possible future station in the city, to be located between Studebaker Road and Gridley Road. I'd like to request that, as part of this action before us today, that a possible future station in Cerritos, between Studebaker Road and Gridley Road, also be included in this assessment.


Issue
ISSUE

A Contract Modification is necessary to conduct technical analysis and provide the outreach and procedural support necessary to complete the federal and state environmental processe...

Click here for full text