File #: 2022-0258   
Type: Motion / Motion Response Status: Passed
File created: 4/15/2022 In control: Board of Directors - Regular Board Meeting
On agenda: 4/28/2022 Final action: 4/28/2022
Title: APPROVE Motion by Directors Hahn, Garcetti, Butts, and Dutra that the Board direct the CEO to update the Measure M Guidelines and First-Last Mile Guidelines in accordance with the following: A. Revise the Measure M Guidelines 3% Contribution calculation to be consistent with the Measure M ordinance; B. In cases where Metro withholds 15 years of Measure M Local Return, clarify that Metro will allow withheld funds to satisfy the 3% contribution via an agreement with the jurisdiction, that jurisdictions may spend withheld funds on First-Last Mile investments, and that those expenses shall be eligible to credit toward a jurisdiction's 15-year total Measure M Local Return obligation in accordance with established Metro procedures, such as the First-Last Mile Guidelines and Measure M Guidelines; C. Confirm that the cost of First-Last Mile improvements delivered by local jurisdictions shall not be included in the "total project cost" from which Metro calculates the 3% Contribution; D. Con...
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Construction, Eric Garcetti, Fernando Dutra, First/Last Mile, Guidelines, James Butts, Janice Hahn, Local Returns, Measure M, Motion / Motion Response, Policy, Project, Transit boards
Meeting_Body
CONSTRUCTION COMMITTEE
APRIL 21, 2022

Preamble
Motion by:

DIRECTORS HAHN, GARCETTI, BUTTS, AND DUTRA

3% Contribution Motion

The Measure M ordinance requires local jurisdictions to pay three percent (3%) of the total project cost of a major Measure M rail project. According to Section 7.f of the Measure M ordinance, each jurisdiction's obligation is calculated "based upon the percent of project total centerline track miles to be constructed within that jurisdiction's borders if one or more stations are to be constructed within the borders of said jurisdiction." This requirement is generally referred to as the "3% Contribution."

Clarifications are necessary to ensure that local jurisdictions fully understand their 3% Contribution calculation and that Metro fully incentivizes local jurisdictions to make First-Last Mile improvements that will benefit Metro projects and increase transit ridership, consistent with Board policy.

First, the Measure M Guidelines (Board File 2017-0280) differ from the Measure M ordinance on how Metro calculates the 3% Contribution. While the Measure M ordinance applies the 3% Contribution only to local jurisdictions where a new station is to be constructed, the Measure M Guidelines extend this obligation to all local jurisdictions within a half-mile of a new station. To ensure clarity, Metro should revise the Measure M Guidelines to be consistent with the Measure M ordinance.

Additionally, not all jurisdictions are presently incentivized to make First-Last Mile investments. Existing Metro Board policy (Board Files 2016-0451 and 2020-0365) seeks to incentivize local jurisdictions to make First-Last Mile investments by allowing the value of those investments to count toward all of a jurisdiction's 3% Contribution obligation. However, as detailed below, this incentive is currently not available to all jurisdictions.

In cases where a jurisdiction's 3% Contribution exceeds 15 years of their Measure M Local Return, per the ...