File #: 2022-0266   
Type: Contract Status: Passed
File created: 4/19/2022 In control: Board of Directors - Regular Board Meeting
On agenda: 6/23/2022 Final action: 6/23/2022
Title: AUTHORIZE the Chief Executive Officer to execute Modification No. 14 to Contract No. OP30433488 with LTK Engineering Services for Technical and Program Management support services for LACMTA A650 Heavy Rail Vehicle Overhaul and Critical Component Replacement Program (OCCRP) to extend the Period of Performance through March 5, 2025 and increase the Not-to-Exceed Total Contract Price by $3,126,944, from $5,488,530 to $8,615,474.
Sponsors: Operations, Safety, and Customer Experience Commit
Indexes: Audit, Board approved Contract, Budgeting, Contractors, Contracts, Procurement, Program, Program Management, Project, Project management, Railroad commuter service, Safety, Test vehicles, Testing, Vehicle performance, Vehicle tests, Witnesses
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification Log, 3. Attachment C - DEOD Summary
Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
JUNE 16, 2022

Subject
SUBJECT: TECHNICAL AND PROGRAM MANAGEMENT SUPPORT SERVICES FOR LACMTA HRV OVERHAUL AND CRITICAL COMPONENT REPLACEMENT PROGRAM

Action
ACTION: APPROVE RECOMMENDATION

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to execute Modification No. 14 to Contract No. OP30433488 with LTK Engineering Services for Technical and Program Management support services for LACMTA A650 Heavy Rail Vehicle Overhaul and Critical Component Replacement Program (OCCRP) to extend the Period of Performance through March 5, 2025 and increase the Not-to-Exceed Total Contract Price by $3,126,944, from $5,488,530 to $8,615,474.

Issue
ISSUE

In October 2016, the Board approved a 46-month contract with LTK Engineering (OP30433488) to support Metro's Project Manager with Technical and Program Management Support services to oversee the rail vehicle overhaul contractor tasked with the A650 OCCRP Project.

Staff requests an extension of the existing consultant contract due to OCCRP project schedule delays. It is necessary to extend the consultant contract to ensure continuity of support for the project and execution of contractual terms for the rail vehicle contractor.

Background
BACKGROUND

On October 27, 2016, the Board approved the contract to be awarded to LTK Engineering in response to RFP No. OP30433488, A650 Consulting Services for Heavy Rail Vehicle Overhaul for Technical and Program Management Support Services. This consultant provides technical program management support to Metro staff engaged in the management of the OCCRP for the overhaul & on-time time delivery of a base order of 74 HRVs.

LTK Engineering is tasked to support Metro's Project Manager with the engineering and technical oversight of the rail vehicle contractor to ensure performance consistent with the delivery requirements of the OCCRP. LTK Engineering provides staff support in the following disci...