File #: 2022-0438   
Type: Contract Status: Consent Calendar
File created: 6/28/2022 In control: Board of Directors - Regular Board Meeting
On agenda: 8/25/2022 Final action:
Title: CONSIDER: A. AUTHORIZING the Chief Executive Officer to award and execute a seven-year contract ending in September 2029, for Contract No. AE82218, with Arcadis Mott MacDonald (AMM) ESFV LRT JV on a Cost Reimbursable Plus Fixed-Fee basis to provide Construction Management Support Services (CMSS) for the East San Fernando Valley (ESFV) Light Rail Transit Project (Project), for an amount of $65,606,451, subject to the resolution of any timely protest; and B. ESTABLISHING Contract Modification Authority (CMA) for $6,560,645 (10%) of the not-to-exceed contract award value and authorizing the CEO to execute individual Contract Modifications within the CMA and within the project budget authorization.
Sponsors: Construction Committee
Indexes: Board certification of Final EIS / EIR, Budgeting, Construction, Construction management, Construction Support, Contract administration, Contractors, Contracts, East San Fernando Valley Light Rail Project, East San Fernando Valley Transit Corridor, Federal Transit Administration, Grant Aid, Housing, Light rail transit, Maintenance, Metro Busway G Line, Metrolink, Partnerships, Procurement, Professional Services, Program Management, Progressive Design/Build, Project, Project delivery, Project management, Public private partnerships, Safety, San Fernando, San Fernando Valley Service Sector, San Fernando Valley subregion, Strategic planning, Van Nuys
Attachments: 1. Attachment A - Procurement Summary RFP No. AE82218, 2. Attachment B - DEOD Summary (004)2022-0438
Related files: 2022-0653

Meeting_Body

REVISED

CONSTRUCTION COMMITTEE

AUGUST 18, 2022

 

Subject

SUBJECT:                     EAST SAN FERNANDO VALLEY LIGHT RAIL TRANSIT PROJECT - CONSTRUCTION SUPPORT SERVICES CONTRACT

 

Action

ACTION:                     APPROVE RECOMMENDATIONS

 

Heading

RECOMMENDATION

 

Title

CONSIDER:

 

A.                     AUTHORIZING the Chief Executive Officer to award and execute a seven-year contract ending in September 2029, for Contract No. AE82218, with Arcadis Mott MacDonald (AMM) ESFV LRT JV on a Cost Reimbursable Plus Fixed-Fee basis to provide Construction Management Support Services (CMSS) for the East San Fernando Valley (ESFV) Light Rail Transit Project (Project), for an amount of $65,606,451, subject to the resolution of any timely protest; and

 

B.                     ESTABLISHING Contract Modification Authority (CMA) for $6,560,645 (10%) of the not-to-exceed contract award value and authorizing the CEO to execute individual Contract Modifications within the CMA and within the project budget authorization.

 

Issue

ISSUE

 

A CMSS is required to provide constructability review, design review support, inspection, estimating, and construction and administration support of the Project to ensure the Project is completed in compliance with contract requirements and applicable government regulations. The CMSS will also provide support for final design, pre-construction activities, administration, pre-revenue service, and contract close-out.

 

Background

BACKGROUND

 

The Project is a light rail system that will extend north from the Van Nuys Metro G-Line station to the Sylmar/San Fernando Metrolink Station, a total of 9.2 miles with 14 at-grade stations.  The Metro Board certified the Final Environmental Impact Report on December 3, 2020.  The Project achieved Record of Decision on January 29, 2021.  The Initial Operating Segment (IOS) is street running in the middle of Van Nuys Boulevard and includes 11 at-grade stations along with the Maintenance and Storage Facility (MSF).  The remaining northern 2.5-mile environmentally cleared segment is going through additional analysis as directed by the Board in December 2020 and is not included in the IOS.

The Project is currently finalizing the preliminary engineering design, with street improvements and guideway design advanced to 60 percent complete and all other design elements (stations, MSF, and systems) to 30 percent complete.  Final design for select advanced utility relocations is also being advanced.  The MSF is comprised of approximately 21 acres and includes several maintenance buildings where Metro will implement a solar photovoltaic (PV) power system via a Public/Private Partnership (P3).

As the IOS has been cleared and the design has advanced, the IOS portion of the Project is proceeding into the next phase of final design and construction. The IOS procurement process for a Progressive Design Build (PDB) Contractor began in July 2022. The CMSS services requested in this item will support execution of the PDB contract once it is awarded in early 2023.

 

Project Delivery Method

 

The Project Delivery Method for the ESFV light rail construction Project will be PDB, a delivery method that was approved by the Board in October 2021 and will be supported by this CMSS contract.  The PDB delivery method has been determined by staff to be the best delivery alternative for the Project, primarily because it is a partnership-based model that will allow Metro and the PDB team to collaborate early, progressively build up the final design of the project, and transparently negotiate the price in an open-books fashion at specific intervals of the design process until a Guaranteed Maximum Price is reached and agreed to. This method will allow Metro to leverage private sector innovation and expertise to identify efficiencies and cost saving opportunities during the next stage of design development. The CMSS consultant is a critical component of the PDB process, as the CMSS team will be providing qualified staff to assist in the PDB process including estimators, construction managers, resident engineers, and professionals experienced in alternative project delivery.

 

The CMSS consultant will also support the proposed P3 contract for the solar PV system at the MSF, as well as stand-alone utility relocation projects performed by third-party agencies or separate contractors.

 

 

Discussion

DISCUSSION

 

Arcadis Mott MacDonald (AMM) ESFV LRT JV, has been selected for recommendation following a competitive procurement process to provide the CMSS in support of the Project.  The scope of services includes administration, inspection services, estimating, and technical support during advanced utility relocations, final design, construction, pre-revenue operations, and closeout phases of the Project.  The primary role of the CMSS consultant is to provide highly skilled and qualified individuals to support and assist Metro with construction management of the Project by becoming part of a fully integrated construction management team residing in the project field office, under the direction of Metro Project Management.  Staff augmentation by the CMSS consultant is necessary to efficiently provide resources and technical expertise that will vary throughout each phase of the Project.

The term of the contract is to support the completion of the PDB and Solar P3 contracts through construction of the projects all the way through the contract closeout process.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

This Board action will have no adverse impacts on safety standards for Metro.  The CMSS contract will provide services that support Metro's internal safety staff on the Project.  The contract provisions require CMSS consultant’s team members to follow the direction of the Metro construction safety policies and procedures to ensure that safety is the highest priority during oversight of all phases of construction.

 

Financial_Impact

FINANCIAL IMPACT

 

This Project is funded on a fiscal year basis under Project number 865521 East San Fernando Valley Transit Corridor, cost center 8510, under various accounts including Professional/Technical Services and $248,236,500 is included in the FY23 Adopted Budget. This is a multi-year project requiring expenditure authorizations in fiscal year increments until a Board Authorized Life of Project Budget is adopted. It is the responsibility of the Cost Center Manager, Project Manager and Chief Program Management Officer to budget for this project in the future fiscal years and within the cumulative budget limit for the affected fiscal year.

 

Impact to Budget

Sources of funds for the recommended actions are a federal grant from the Federal Transit Administration (FTA) Expedited Project Delivery (EPD) Pilot Program, State Grants and Measure M 35%. These funds are not eligible for bus and rail operations.

 

 

 

 

 

Equity_Platform

EQUITY PLATFORM

 

The Project study area’s average transit-dependent population of 7.04 persons per acre is more than 100 percent higher than the 3.21 County average. The Project will provide new reliable service and/or infrastructure that improves passenger mobility and enhances transit accessibility/connectivity for residents within the Project study area to local and regional destinations and activity centers. This contract will facilitate Project construction and the Progressive Design/Build delivery method is not anticipated to have any adverse impacts to engagement or mitigation opportunities for the surrounding communities.

 

To ensure maximum opportunity for participation on this contract, Metro staff performed extensive outreach to the small business community, including those within the Disadvantaged Veterans Business Enterprise and the Small Business Enterprise programs. The solicitation was advertised through periodicals of general circulation, posted on Metro’s Vendor Portal, and an e-mail notice to small businesses with applicable NAICS codes. The Proposal Evaluation Team was comprised of department personnel that were both race and gender diverse. The selected firm committed to achieving a Disadvantaged Business Enterprise (DBE) goal of 30.05% through 9 identified subcontractors. This commitment exceeds the DEOD recommended goal of 28%.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The Project supports the following strategic goals:

Strategic Goal 1: Provide high-quality mobility options that enable people to spend less time traveling. The purpose of the Project is to provide a high-capacity transit service in the San Fernando Valley.

Strategic Goal 2: Deliver outstanding trip experiences for all users of the transportation system. The at-grade light rail system will attract bus ridership and improve the trip experience for users of the transportation system.

Strategic Goal 3: Enhance communities and lives through mobility and access to opportunity. With 11 stations, including connections to Metro G-Line and Metrolink, the ESFV enhances mobility to the community

Strategic Goal 4: Transform LA County through regional collaboration and national leadership. Collaboration with the elected officials, citizens, and Metro patrons of San Fernando Valley continues to positively impact the Project.

 

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board could direct Metro staff to perform construction support tasks with current in-house resources. However, this alternative is not recommended or feasible, as Metro does not currently have available in-house resources with expertise in the negotiation, estimation, and delivery of alternative delivery contracts such as Progressive Design-Build. The FY23 budget does include several new positions in Program Management for this project; however, these positions are primarily for Project Management, Program Controls, and Engineering and the CMSS is still required. Program Management will continue to manage the consultant/staff balance as we continue to on-board new staff and Metro full-time equivalents.

 

Next_Steps

NEXT STEPS

 

After the recommended Board actions are approved, staff will complete the process to award Contract No. AE82218.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - DEOD Summary

 

Prepared_by

Prepared by::                     

 

Monica Born, Deputy Executive Officer, Program Management, (562) 524-0597

 

 

Reviewed_By

Reviewed by:                      

 

Bryan Pennington, Chief Program Management Officer, (213) 922-7557

James Dela Loza, Chief Planning Officer (213) 922-2920

Debra Avila, Deputy Chief, Vendor/Contract Management Officer, (213) 418-3051