File #: 2023-0101   
Type: Informational Report Status: Filed
File created: 2/10/2023 In control: Finance, Budget and Audit Committee
On agenda: 3/15/2023 Final action: 3/15/2023
Title: RECEIVE AND FILE the Fiscal Year 2024 (FY24) Budget Development Status Update.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budgeting, Construction, Informational Report, Project, Strategic planning
Attachments: 1. Attachment A - Transit Infrastructure Development Project Details, 2. Attachment B - Highway Multimodal Development Project Details, 3. Attachment C - Public Engagement Update, 4. Presentation

Meeting_Body

FINANCE, BUDGET, AND AUDIT COMMITTEE

MARCH 15, 2023

 

Subject

SUBJECT:                     FISCAL YEAR 2024 BUDGET DEVELOPMENT STATUS UPDATE

 

Action

ACTION:                     RECEIVE AND FILE

 

Heading

RECOMMENDATION

 

Title

RECEIVE AND FILE the Fiscal Year 2024 (FY24) Budget Development Status Update.

 

Issue
ISSUE

 

This is the third of a series of monthly updates to the Board on the FY24 Budget development process, culminating in a planned May 2023 Board Adoption.  This report lays the framework for the annual budget development, with the primary objective for the annual budget to advance Metro’s transit and transportation goals, with an equity lens, in a fiscally sound and financially responsible manner. 

This report focuses on Metro’s diverse portfolio of major infrastructure capital projects, including Transit Infrastructure Development (TID), Highway Multimodal Development, and Regional Rail. Additionally, this report provides an overview of Metro’s voter approved Regional Allocation and Pass Throughs (Subsidy) funding programs.

This report also discusses the mitigation options to be considered for managing through the near-term financial challenges for the major infrastructure capital projects and shares the latest update regarding Metro’s comprehensive budget outreach efforts.

 

Background

BACKGROUND

 

California Public Utilities Code Section 130105 requires Metro to adopt an annual budget to manage the revenues and expenses of the Agency’s projects and programs. The budget is the legal authorization to obligate and spend funds and to implement Board policy. It includes all operating, capital, planning and programming, subsidy funds, debt service requirements, and general fund activities for the fiscal year.  The legal level of control is at the fund level. Total annual expenditures cannot exceed the final appropriation by the Board at the fund level except for capital expenditures, which are authorized on a life of project basis.

 

Discussion

DISCUSSION

 

Major Infrastructure Capital, Near-Term Financial Challenges

 

Metro recognizes the importance of sound financial planning to successfully implement transit capital investments and operating plans. The overall operating deficit also referred to as the ‘fiscal cliff,’ and the challenges of major infrastructure capital projects, are two distinct concerns impacting Metro. In this report, we will be discussing the challenges regarding major infrastructure capital projects. The operating deficit will be presented in next month's report.

Metro recognizes the additional financial risks stemming from Transportation Infrastructure Development (TID) as we continue to build out the ordinance approved major construction projects.  While the cashflow required in the next three-year near term is not at risk, Metro needs to be mindful of the total project costs and potential funding gaps faced by each project over the next ten years and beyond so as to not be obligated to a project delivery ahead of the funding plan.  Currently, Measure R and M total receipts are below their ordinance projections. Although Metro continues to compete for capital investment grants, not all of Metro’s projects are awarded funding. Grants awarded to Metro often include significant operational and local match funding requirements placed in the legal framework for the funding agreement. Additional debt issuance is projected from FY24 to FY26 to cover shortfalls in certain programs; however, new debt issuance will only be used as a last resort as it is subject to Board established maximum bonding capacity policy and potentially means reduced future funding availability for other transit needs.

Other common capital project management issues include higher bid prices and cost increases due to a tighter labor market and rising demand for goods with previous supply chain constraints. Capital projects are also impacted by fiscal challenges that may increase total project cost at completion. Project cost overruns with no new or dedicated funding will continue to take away funding currently available for transit. These combined challenges in capital infrastructure, along with the stressors in the operating budget deficit, have contributed to the Agency's overall financial outlook.

 

Major Infrastructure Capital, EZBB Cost Control

Metro is enacting cost controls through the Equitable Zero-Based Budgeting (EZBB) process by establishing the Early Intervention Team and other program management efforts.

At Board’s direction, the CEO formed the Early Intervention Team (EIT), which is set up to draw on the collective experiences of cross department collaboration to review and assess cost and schedule drivers, potential corresponding mitigation strategies currently in practice at Metro, as well as new mitigation strategies needed across the full life cycle of projects, from planning through construction and finally into operations and maintenance. Regular updates are being provided to the board on the status and progress of these efforts.

Metro is actively evaluating the appropriate consultant to staff ratio that can build up in-house knowledge. Metro is also strategically embedding seasoned project management and controls staff onto new major projects as other projects are exiting the construction phase and moving on to the operational phase. There is also ongoing project soft cost monitoring and reporting.

 

Major Infrastructure Capital, Near-Term Mitigation Strategies for Consideration

Below are some other mitigation strategies to help address the challenges described above.

Transit Infrastructure Development:

•                     Project Timeline: Deliberate board review at each major project milestone; assess the cost/benefit of changing project schedules as necessary while remaining within sequence per ordinance.

•                     Project Scope: Avoid adding additional components beyond the original project scope to remain within budget.

•                     Operational Impact: Plan and incorporate the cost implications of system integration due to an expanding system.

•                     Business Interruption Fund (BIF): Advocate for BIF funds to be eligible to match and/or be eligible for reimbursement of state and federal funds.

Highway Multimodal Development:

•                     Strategic Partnership with Caltrans:  Work with Caltrans to explore efficiencies to deliver the highway projects based upon core competencies.    

 

 

Regional Rail:

•                     Metrolink Operating Plan:  Align service level goals to ridership demand with a financially sustainable operating framework to mitigate the structural deficit in eligible funding sources Metro utilizes to finance Metrolink operations.  

 

Major Infrastructure Capital Investment FY24 Preliminary Budget

LA County’s capital expansion plan is one of the nation’s most ambitious and transformative transportation construction and enhancements programs. The report below covers the following programs:

1.                     Transit Infrastructure Development (TID): The FY24 Budget provides funding for planning and constructing new transit projects for LA County per the voter approved Measure R and Measure M sales tax ordinances. In FY23, this program reflected 26.5% of the total FY23 budget.

2.                     Highway Multimodal Development: The FY24 Budget provides funding from voter approved Measure R and Measure M sales tax ordinances to advance design and construction activities for Highway projects in LA County, notably the I-105 ExpressLanes, I-5 North Capacity Enhancements Project, and community-driven efforts to re-imagine the I-710 North, I-710 South, and I-605 Hot Spots Projects. In FY23, this program reflected 6.6% of the total FY23 Budget.

3.                     Regional Rail: The FY24 Budget supports double tracking and grade separation projects transitioning from Final Design to pre-construction activities, advancing the transformative Link Union Station project, and ongoing subsidy support for Metrolink’s operating and SGR/capital components. In FY23, this program reflected 3.3% of the total FY23 Budget.

In FY23, major infrastructure capital projects totaled 36.4% of the Metro budget. The FY24 Preliminary Budget represents the annual incremental cashflow requirement to advance these capital projects.

 

Transit Infrastructure Development (TID)

 

The TID Program consists of transit line expansions and improvements specified in the Measure R (MR) and Measure M (MM) Ordinances. These project development activities are divided into planning and construction phases, and the annual budget request reflects the annual increments of the project development phase. Starting with a feasibility study followed by alternative analyses, the planning phase typically culminates in environmental clearance.  The multiyear Life Of Project (LOP) budget is adopted for each project through a separate board action.

The annual budget monitors the cashflow requirement for the activities in each project phase while considering the existing level of board authorization(s), respective project delivery schedule and identifies eligible and available funding sources from Federal/State/Local grants, sales taxes, and financing.

Fig 1:

 

For FY24, Figure 1 above displays the preliminary budget for the TID program at $2.19 billion, a decrease of $113.4 million or 4.9% from the FY23 budget. The decrease in the Transit Construction budget reflects the opening of the Regional Connector in FY23 while newer projects, including the East San Fernando Valley Light Rail Transit project project has yet to proceed into the major construction phase. While the budget for transit construction decreased, the budget for planning studies increased by $105.6 million, or 61.3%, which reflects increased funding for planning projects in the environmental and design phase, including the Sepulveda Corridor, West Santa Ana Branch and Eastside Transit Corridor Phase 2 projects. These projects will also advance to requiring funds for construction in future fiscal years, and thus this year’s requested budget reflects current project phasing and not a broader pattern.

A more detailed project discussion can be found in Attachment A.

 

Highway Multimodal Development

 

The FY24 Preliminary Budget of $606.3 million represents a $27 million or 4.7% increase over the FY23 Adopted Budget.  The FY24 preliminary budget reflects a transitional period for Metro’s Highway program as the Agency begins to shift away from legacy highway expansion projects and towards investments in ExpressLanes and HOV construction, improvements to bus infrastructure, including bus-only lanes, and safety enhancements.  Further, a shift in eligibility criteria for Metro freeway and street programs enables municipalities and partner agencies to incorporate multimodal components in the surface street and subregional road improvement projects. 

In FY24, the Highway Multimodal Development budget advances design activities and pre-construction activities for the I-105 ExpressLanes project, the implementation of additional bus-only lanes and bus infrastructure throughout LA County, re-imagining the I-710 South and I-605 Hot Spots projects, and ongoing construction for the I-5 South and I-5 North freeways, as well as the SR-57/SR-60 confluence project. 

 

 

Fig 2:

 

See Attachment B for individual Highway project detail. 

 

Metro Regional Rail

 

Metro oversees the planning, programming, and implementation of commuter rail projects in LA County that are or will be operated by other agencies such as Southern California Regional Rail Authority (Metrolink), Amtrak, California High Speed Rail Authority, and freight carriers. Metro also manages and coordinates capital improvement projects along approximately 150 miles of Metro owned, and Metrolink operated railroad right-of-way.

 

Fig 3: