Meeting_Body
CONSTRUCTION COMMITTEE
NOVEMBER 16, 2023
Subject
SUBJECT: RAIL TO RAIL ACTIVE TRANSPORTATION CORRIDOR PROJECT
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
CONSIDER:
A. INCREASING the Life of Project Budget for the Rail-to-Rail Active Transportation Project (Project) by $23,100,000, from $143,284,000 to $166,384,000; and
B. AUTHORIZING the Chief Executive Officer to execute agreements, including Contract Modifications, within the Board Approved Life of Project Budget.
Issue
ISSUE
The Life of Project (LOP) budget for the Rail-to-Rail Active Project requires an increase of $23,100,000 for additional costs related to the remediation and disposal of unanticipated hazardous soils, differing site conditions within the public intersections, additional professional services, and third-party costs to provide oversight of the Project through completion.
Background
BACKGROUND
The Rail-to-Rail Active Transportation Project is a dedicated walkway and bikeway approximately 5.6 miles in length that begins at the Metro K Line Florence/West Station and stretches east along the Harbor Subdivision rail right-of-way following Slauson Avenue from Inglewood through South Los Angeles, terminating at the Metro A Line Slauson station. This new east-west pedestrian and bicycle corridor will connect travelers to three major Metro transit lines - the A (Blue) Line, K (Crenshaw) Line, and J (Silver) Line - and multiple bus lines. As of this report, the Project is approximately 35% complete and remains on schedule for a Winter 2024 opening.
In January 2022, the Board approved a Life of Project budget of $115,989,000. The budget assumed that the City of Los Angeles (City) would complete all construction work within the public right-of-way and that Metro and the City would execute a Memorandum of Understanding memorializing this arrangement. However, after approval of the LOP, Metro and the City mutually agreed to pursue a direct fi...