Subject
SUBJECT: SOUTHEAST GATEWAY LINE
Action
ACTION: APPROVE CONTRACT AWARD
Heading
RECOMMENDATION
Title
AUTHORIZE the Chief Executive Officer (CEO) to award a cost-plus fixed fee contract, Contract No. AE107133000, for a period of 5 years, with two, 5-year options, to WSP USA, Inc., for Program Management Support Services (PMSS) for the Slauson/A Line to Pioneer segment of the Southeast Gateway Line Project (formerly referred to as the West Santa Ana Branch Transit Corridor) in an amount not to exceed $99,999,105, subject to the resolution of any properly submitted protest(s), if any.
Issue
ISSUE
Staff is seeking the Board's approval of a contract award to provide program management and construction management support services to meet the Board's expectation of delivering the Locally Preferred Alternative (LPA) segment of the Southeast Gateway Line Project, formally known as West Santa Ana Branch Project. It allows staff to continue the momentum already established in our ongoing coordination with third-party stakeholders, which is key to ensuring the successful completion of project-related agreements.
Background
BACKGROUND
The Project roadmap is comprised of the following parallel workstreams:
* Planning - completing final environmental clearance,
* Early Due Diligence (EDD) - addressing high risk items such as utilities, unknown soils conditions, and third-party agreements, and
* LRT Project Delivery - continuing to evaluate various contract delivery methods most beneficial to Metro.
A component of the EDD workstream includes the award of several contracts to address the high-risk elements of the project prior to the light rail construction. The Advanced Engineering (AE) contract was the first of those contracts and was approved by the Board in November 2023. While the AE contract provides design services to support Metro's efforts in meeting FTA requirements to advan...