Meeting_Body
CONSTRUCTION COMMITTEE
JULY 17, 2024
Subject
SUBJECT: SUPPLEMENTAL ENGINEERING SERVICES (SES) CONSULTANT SERVICE CONTRACT
Action
ACTION: AWARD PROFESSIONAL SERVICES CONTRACT
Heading
RECOMMENDATION
Title
AUTHORIZE the Chief Executive Officer to:
A. AWARD a cost plus fixed fee Contract No. AE120356 to HDR Engineering, Inc. for Supplemental Engineering Services for Engineering Design of Transit Rail Projects on a task order basis, in an amount not to exceed $50,000,000 for the base three-year term, and $10,000,000 for each of the two, one-year options, for a total contract value not to exceed $70,000,000, subject to resolution of any protest(s), if any; and
B. ISSUE individual Task Orders and modifications within the Board approved contract amount.
Issue
ISSUE
Metro's staff engineers, architects and CADD designers in the Engineering Group are fully engaged supporting our current Major Rail Transit Projects (Purple Line Sections 1, 2, and 3), East San Fernando Valley Light Rail Transit Project, Airport Metro Connector, Foothill Extension, Metro Center Project, Division 20 Portal Widening, Metro G Line Improvements Project, Link Union Station (Link US), North Hollywood to Pasadena BRT and numerous other capital improvement and state of good repair projects.
In addition, the major transit capital expansion programs within Measure M have added a considerable workload to the Metro Engineering group with many projects that will shortly be transitioning towards or moving into the Program Management phase such as the C-Line Extension, the Southeast Gateway Line, Sepulveda Transit Corridor, and the Eastside Phase II projects, as examples.
In order to move Metro's ambitious transit expansion programs forward, supplemental engineering services are required.
Background
BACKGROUND
The existing Supplemental Engineering Services (SES) contract (Contract No. AE59600) will expire on July 25, 2024. The authorized funding for this existing con...
Click here for full text