2021-0543
| 28. | Contract | CONSIDER:
A. FINDING that authorization of the use of alternative delivery methods, including Progressive Design-Build (PDB), will achieve integration of design, project works, and other components in an efficient manner the East San Fernando Valley (ESFV) Light Rail Transit Project (Project) pursuant to Public Utilities Code Section 130242; and
B. APPROVING a competitive solicitation of a PDB contract to achieve the proposed design approach, specific project features and functions, and other project criteria in addition to price, pursuant to Public Utilities Code 130242 (e).
(REQUIRES 2/3 VOTE OF THE FULL BOARD) | | |
Not available
|
Not available
|
2021-0544
| 29. | Contract | CONSIDER:
A. FINDING that authorization of the use of Public/Private Partnership (P3) will achieve the design, build, finance, and participation in oversight of Operation and Maintenance of solar photovoltaic (PV) power (commonly known as solar panels) generation system at the Maintenance and Storage Facility for the East San Fernando Valley Transit Corridor Project (ESFV) pursuant to Public Utilities Code Section 130242; and
B. APPROVING a competitive solicitation of a P3 contract to achieve the proposed design, specific features and functions, and other qualifications in addition to price, pursuant to Public Utilities Code Section 130242. | | |
Not available
|
Not available
|
2021-0572
| 30. | Contract | AUTHORIZE the Chief Executive Officer to:
A. AWARD AND EXECUTE a three-year cost plus fixed fee contract, Contract No. AE76301MC081 with Zephyr Rail, to provide Construction Management Support Services for Capital Projects, in an amount not-to-exceed $3,519,211.94 for the three-year base period, plus two (2) one-year options if deemed appropriate, subject to resolution of any properly submitted protest(s); and
B. EXECUTE individual Task Orders within the Board approved not-to-exceed amount. | | |
Not available
|
Not available
|
2021-0686
| 31. | Motion / Motion Response | APPROVE Motion by Directors Hahn, Dupont-Walker, Butts, Mitchell, Dutra, and Kuehl that directs the CEO to:
A. Survey local preference best practices nationally and make recommendations for local preference criteria;
B. Evaluate and recommend changes to Metro policies regarding advancing local preference in small, medium, and disadvantaged business contracting;
C. Review State and Federal laws and regulations and make recommendations for inclusion in future Federal and State Legislative Priorities; and,
D. Report back on these requests in February 2022. | | |
Not available
|
Not available
|
2021-0610
| 32. | Oral Report / Presentation | RECEIVE oral report on the Major Project Status by the Chief Program Management Officer. | | |
Not available
|
Not available
|
2021-0580
| 33. | Informational Report | RECEIVE AND FILE status report on Program Management Quarterly Change Report. | | |
Not available
|
Not available
|
2021-0591
| 34. | Informational Report | RECEIVE AND FILE Office of the Inspector General Change Order Construction Spot Check Report for the period June 1, 2021 to August 31, 2021. | | |
Not available
|
Not available
|
2021-0643
| | Informational Report | RECEIVE General Public Comment | | |
Not available
|
Not available
|