Meeting Name: Construction Committee Agenda status: Final
Meeting date/time: 10/23/2024 2:00 PM Minutes status: Draft  
Meeting location: One Gateway Plaza, Los Angeles, CA 90012, 3rd Floor, Metro Board Room
Watch online: https://boardagendas.metro.net Listen by phone: Dial 202-735-3323 and enter Access Code: 5647249# (English) or 7292892# (Español) To give written or live public comment, please see the top of page 4
Published agenda: Agenda Agenda Published minutes: Not available  
Meeting video: eComment: Not available  
Attachments:
File #Agenda #TypeTitleActionResultAction DetailsAudio
2024-0910 16.Informational ReportRECEIVE AND FILE status report on the Program Management Quarterly Change Report.   Not available Not available
2024-0926 17.BudgetINCREASE the Life-of-Project (LOP) budget for the Regional Connector Transit Corridor Project (Project) by $39,000,000 from $1,755,840,570 to $1,794,840,570 to fully resolve claims and complete the close out the Project.   Not available Not available
2024-0527 18.BudgetINCREASE the Life-of-Project (LOP) budget by $99,730,000 for the Division 20 Portal Widening Turnback Facility (Project) from $956,749,577 to $1,056,479,577 using the fund sources as summarized in Attachment A, consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B).   Not available Not available
2024-0857 19.BudgetAUTHORIZE the Chief Executive Officer to: A. ESTABLISH the I-105 ExpressLanes Project 475004 Life-of-Project (LOP) Budget by increasing the existing Preconstruction Budget and by establishing funding for the Segment 1 (Identified Work Package 1) construction, from Sepulveda Blvd. to Central Avenue on the I-105 Freeway. This action increases the existing Preconstruction Budget of $119,391,538 by $638,148,678 to a Life-of-Project Budget of $757,540,216 (Attachment A); B. NEGOTIATE AND EXECUTE project-related agreements, including contract modifications, up to the authorized LOP; C. ESTABLISH an LOP budget of $44,254,826 for the I-105 Express Lanes project segments 1, 2, and 3 Roadside Toll Collection System (RTCS) Project 275004; and D. AMEND FY25 budget for Project 475004 by $47,234,197 from $126,112,511 to $173,346,708 and for Project 275004 by $3,824,193 from $2,129,990 to $5,954,183.   Not available Not available
2024-0993 20.ContractAUTHORIZE execution of Amendment No. 4 to the Funding Agreement between the Metro Gold Line Foothill Extension Construction Authority ("Authority") and the Los Angeles County Metropolitan Transportation Authority ("Metro") to reflect the allocation of $798,000,000 of the California State Transportation Agency (“CalSTA”) Transit and Intercity Rail Capital Program (“TIRCP”) formula funding authorized by Senate Bill 125 (“SB125 Funds”).   Not available Not available
2024-0553 21.Oral Report / PresentationRECEIVE the quarterly oral report on the status of the Caltrans construction projects.   Not available Not available
2024-0531 22.Oral Report / PresentationRECEIVE AND FILE the Program Management Project Status Report.   Not available Not available