Meeting Name: Construction Committee Agenda status: Final
Meeting date/time: 4/20/2023 11:00 AM Minutes status: Draft  
Meeting location: Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room
Watch online: https://boardagendas.metro.net Listen by phone: Dial 888-251-2949 and enter Access Code: 8231160# (English) or 4544724# (EspaƱol) To give written or live public comment, please see the top of page 4
Published agenda: Agenda Agenda Published minutes: Not available  
Meeting video: eComment: Not available  
Attachments:
File #Agenda #TypeTitleActionResultAction DetailsAudio
2022-0509 22.BudgetAMEND the Life-of-Project (LOP) Budget by $10,000,000 for the Crenshaw/LAX Close Out Project (Project), increasing it from $47,000,000 to $57,000,000.   Not available Not available
2023-0100 29.BudgetAMEND the Life of Project (LOP) budget by $13,000,000 for the Metro Center Project from $130,688,310 to $143,688,310.   Not available Not available
2022-0858 24.ProgramCONSIDER: A. RECEIVING AND FILING the Pilot Business Interruption Fund (BIF) Assessment; B. AUTHORIZING the Chief Executive Officer to expand the Pilot Business Interruption Fund (BIF) to the East San Fernando Valley Light Rail Transit Project; and C. APPROVING the Pilot Business Interruption Fund (BIF) program modifications (Attachment D).   Not available Not available
2023-0159 23.BudgetCONSIDER: A. AMENDING the Life of Project Budget (LOP) Budget for Project No. 460324 Soundwall Package 11 Highway Project by an amount of $8,525,000, increasing the LOP budget from $102,485,000 to $111,010,000, consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B); and B. AUTHORIZING the Chief Executive Officer to execute individual Contract Modifications within the Board approved Life of Project budget.   Not available Not available
2023-0176 27.Informational ReportRECEIVE AND FILE status on Program Management Quarterly Change Report.   Not available Not available
2023-0177 30.Oral Report / PresentationRECEIVE AND FILE Program Management Major Project Status Report.   Not available Not available
2023-0197 26.BudgetAMENDING the Life-of-Project (LOP) budget by $80,000,000 for the Division 20 Portal Widening Turnback Facility (Project) from $876,749,577 to $956,749,577 using the fund sources as summarized in Attachment A, consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B).   Not available Not available
2023-0111 28.Informational ReportRECEIVE AND FILE Office of the Inspector General Construction Change Order Spot Check Report for the period December 1 to February 28, 2022.   Not available Not available
2023-0009 25.BudgetAUTHORIZE The Chief Executive Officer to: A. AWARD AND EXECUTE a cost reimbursable fixed fee Contract No. AE83177E0130, to Jacobs Project Management Company, for preconstruction services and construction management support services on the Link US Project; B. AUTHORIZE a contract amount not-to-exceed $16,250,000 through January 2027 to support preconstruction services with an initial Annual Work Plan not to exceed $3,051,600; and C. NEGOTIATE AND EXECUTE contract modifications within the Board approved contract funding amount.   Not available Not available
2023-0234  Informational ReportRECEIVE General Public Comment   Not available Not available