Meeting_Body
REGULAR BOARD MEETING
MAY 25, 2017
Subject/Action
SUBJECT: EASTSIDE TRANSIT CORRIDOR PHASE 2
ACTION: APPROVE TECHNICAL STUDY RECOMMENDATIONS
Heading
RECOMMENDATION
Title
CONSIDER:
A. APPROVING an updated Project Definition for Environmental Clearance, including three alternatives:
1. SR 60 North Side Design Variation Alternative;
2. Washington Boulevard Alternative with Atlantic Below-Grade Option; and
3. Combined Alternative with both SR 60 and Washington Boulevard via Atlantic Segments; and
B. RECEIVING AND FILING the Eastside Phase 2 Technical Study Report. Attachment D contains the Executive Summary. The full report is available upon request.
Issue
ISSUE
In November 2014, the Board received the Eastside Transit Corridor Phase 2 Draft Environmental Impact Statement/Report (EIS/EIR) and approved carrying forward to further study two build alternatives: the SR 60 North Side Design Variation (NSDV) Alternative and the Washington Boulevard Alternative. Staff was directed to address comments received from Cooperating and Public Agencies, identify an alternative to the Washington Boulevard Garfield Alternative aerial alignment, and analyze the feasibility of operating both alternatives.
At the July 2015 meeting, the Board approved a Contract Modification for the Metro Eastside Transit Corridor Phase 2 Project to undertake this work including community outreach to support the Technical Study. The Board also approved a motion (Attachment A) directing staff to provide bi-monthly updates on the project covering:
• analysis and refinement of project alternatives,
• project schedule and milestones,
• status reports on work with third-party agencies, and
• community outreach.
The Eastside Phase 2 Technical Study is now complete, and includes findings and recommendations for Board consideration. Specifically, Board approval is being sought to adopt the updated Project Definition, which includes a slightly revised SR 60 North Side Design Variation Alternative and the Atlantic Boulevard Underground Option as the new Washington Boulevard Alternative. The updated Project Definition also includes a ‘Combined’ Alternative, which is recommended for further study in the next phase of work. Board selection of a Locally Preferred Alternative (LPA) will be made upon the completion of the revised draft environmental documents.
Discussion
DISCUSSION
Project Schedule and Milestones
The major work elements described above for this project had several key milestones. The Technical Study incorporated extensive stakeholder feedback into the screening analysis which informed the technical recommendation made herein. Attachment B summarizes the completed milestones. The project team undertook numerous investigations and design studies to address comments received from the Cooperating agencies and the November 2014 Board direction. Based on the findings of these technical investigations and consultation with Resource Agencies, there are no significant outstanding issues otherwise preventing the re-initiation of the environmental process on the updated Project Definition.
Status Report
SR 60 North Side Design Variation (NSDV) Alternative
The project team undertook a coordinated design refinement effort to address potential conflicts with other plans and existing facilities. Much of the effort focused on the NSDV segment between Greenwood Avenue and Paramount Boulevard, which was modified to address several areas of concern. The City of Monterey Park and the Monterey Park Market Place developer expressed concerns that the original NSDV might block the view of the Market Place development just north of the proposed NSDV alignment limits. The project team modified the alignment geometry, lowered the grade profile in front of the proposed Market Place development, and relocated the proposed NSDV eastern flyover further east. Also, the guideway over the Paramount Boulevard on-ramp was slightly realigned to avoid conflicts with the widened on-ramp currently in construction, per request of California Department of Transportation (Caltrans). In unincorporated East Los Angeles, to minimize visual obstruction to the AltaMed’s PACE facility on Pomona Boulevard at Hillview Avenue, the study team refined the guideway alignment by shifting the proposed beginning of the retaining wall further east by approximately 350 feet.
In addition, the project team completed numerous technical investigations to address issues arising from comments received from Cooperating Agencies, including:
• subsurface investigation along the western portion of the NSDV guideway alignment to document soil conditions, per request by United States Environmental Protection Agency (EPA);
• field surveys to confirm the height of Southern California Edison (SCE) transmission lines crossing SR 60 just east of Paramount Boulevard and inform the development of a preliminary plan to raise the SCE transmission lines to a height sufficient to remove the clearance conflict;
• sensitive species, rare plants and jurisdictional waters surveys, per request by EPA and the California Department of Fish and Wildlife (CDFW); and
• advancement of concept design of the proposed Santa Anita Station and Park and Ride facility to address issues related to flood management operational flexibility, per request by the Unites States Army Corps of Engineers (ACE)
This effort included extensive consultation with each of the key Cooperating Agencies that included a review of work plans, incorporation of technical feedback and disclosure of preliminary findings.
Based on the results of the technical investigations, design refinements and feedback received from Cooperating Agencies and key stakeholders, it is recommended that the Project Definition be updated to include the revised SR 60 NSDV Alternative. The technical work performed on the SR 60 NSDV Alternative has addressed Cooperating Agency comments to a degree sufficient to justify the study of this updated Alternative in a re-initiated environmental document.
Washington Boulevard Alternative: Route Options Screening Results
The project team completed an evaluation of potential Washington Boulevard connection options. The process started with 27 potential connection options to Washington Boulevard, including 17 options from the 2009 Alternatives Analysis (AA) study and 10 new options not previously considered. These 27 route options were evaluated based on physical constraints such as street widths, utilities and existing structures. In addition, the assessment considered factors such as ridership, cost, travel time, access to major activity centers, economic development opportunities, Transit-Oriented Communities (TOC) potential, and consistency with community goals. Based on the analysis and the feedback provided from the study area key stakeholders, three route options - Garfield, Atlantic and Arizona - stood out as most promising and were the subject of more detailed technical analysis (Attachment C). These three north-south connection options were shared at community meetings held in March 2016, June 2016 and February 2017.
The following highlights key findings and recommendations, which are informed both by technical analysis and feedback received from the communities and stakeholders:
• Garfield Route Option: The design of an underground configuration along Garfield Avenue would require a tight horizontal curve just west of Via Campo and Wilcox Avenue, which could potentially impact the existing commercial site and the Ford dealership. South of this location, an underground tunnel would require the relocation of storm drains and sewer lines along Garfield Avenue. From a ridership standpoint, the catchment area around a proposed Metro station at Garfield Avenue and Whittier Boulevard lacks the intensity of activity typically associated with a subway station. Moreover, the alignment misses the Commerce Citadel and Casino area, which has the study area’s highest ridership potential. With an underground tunnel, there would also be significant impacts during construction, including property acquisition, business disruption and traffic/circulation impacts near SR 60. As a result, the Garfield Underground Option is not recommended for further consideration as a potential north-south connection to Washington Boulevard.
• Arizona Route Option: Although Arizona Avenue is a wide street (108” curb to curb), it is located in a low-density residential district where on-street parking is an important community asset. A median-running at-grade light-rail transit (LRT) would necessitate the removal of on-street parking. This would create a significant hardship to residents along Arizona Avenue. From an operational standpoint, there are also significant challenges associated with a junction at 3rd Street and Mednik Avenue, which is just west of the existing East LA Civic Center Station and the intersection where Griffith Middle School is located. A junction on Arizona Avenue would necessitate demolishing and shifting the LA Civic Center Station east of its current location with potential property impact to the northwest corner of the Griffith Middle School.
A below-grade configuration on Arizona Avenue would avoid the on-street parking loss impacts associated with at-grade LRT, but would require the taking of numerous residences in the vicinity of 3rd Street and Mednik Avenue, where there would be need to be a large construction site to launch or extract a tunnel boring machine (TBM) and a permanent tunnel portal. It is determined that an underground LRT portal on Arizona Avenue could not be constructed and operated without permanent residential property displacements. While there is some potential for economic development around a proposed Metro station at Arizona Avenue and Whittier Boulevard, the existing catchment area lacks the intensity of activity typically needed to justify the investment in an underground Metro station. Based on the preponderance of factors considered above, any LRT extension along Arizona Avenue would not be consistent with community priorities and goals. As a result, Arizona is not recommended for further consideration as a potential north-south corridor connection to Washington Boulevard.
• Atlantic Route Option: Atlantic Boulevard possesses land use characteristics and activity levels best suited for premium Metro rail service. It is a medium density commercial/retail corridor that is narrower than Arizona Avenue, but intersects with the historic Whittier Boulevard corridor. The catchment area around Atlantic Boulevard and Whittier Boulevard is a vibrant hub of retail activity, and has strong economic development potential. Because Atlantic Boulevard is a major arterial corridor with heavy traffic, it is not a viable corridor for at-grade LRT, especially given the presence of numerous sensitive uses (schools and churches). A grade crossing analysis was conducted which indicated that at-grade LRT would produce significant traffic/circulation and access impacts that could not be mitigated. The project team investigated the feasibility of a below-grade configuration that would connect the Atlantic Station to the thriving Whittier Boulevard commercial corridor and the regional-serving Commerce Citadel and Hotels complex in the City of Commerce. The Atlantic below-grade option would offer the benefit of avoiding numerous physical obstacles, including: the Mixmaster (the junction of Atlantic Boulevard, Triggers Street, Telegraph Rd., and Union Pacific Railroads), the AltaMed’s Headquarters facilities on Camfield Avenue, the SCE transmission towers east of Tubeway Avenue and a number of BNSF rail spurs in the eastern part of the City of Commerce.
The study team explored several potential methods of constructing a rail tunnel, including launching a TBM from the south in the City of Commerce and extracting it from the north near Atlantic Boulevard and 3rd Street where a portal is needed to allow trains to daylight from a tunnel. This construction approach could significantly reduce the footprint needed for tunnel construction staging in East Los Angeles. In addition, the City of Commerce has expressed openness to exploring joint development opportunities made possible through the acquisition of parcels needed for a maintenance facility in the eastern part of the City of Commerce north of Washington Boulevard. For these reasons, the Atlantic Underground Option is the most promising north-south connection to Washington Boulevard, and is recommended for Board approval as the new Washington Boulevard Alternative.
The table below summarizes the screening results of the Washington Boulevard route options - Arizona, Atlantic and Garfield (underground) - and compares them to the Washington Boulevard Alternative in the Draft EIS/EIR.
The Arizona and Garfield Route Options are not recommended for further consideration as they are fundamentally inconsistent with community goals. The Atlantic Underground Option provides the most benefits when compared to other options studied for the Washington Alternative. The Atlantic Underground Option performs well on a number of key measures including projected high ridership (19,610 to 21,070 boardings), faster travel time (17-18 minutes), best meets community goals by minimizing surface operational disruptions and providing connectivity to local and regional destinations and activity centers in unincorporated East Los Angeles and the City of Commerce.
The cost estimate for the Washington Boulevard Alternative via Garfield Avenue from the 2014 Draft EIS/EIR was approximately $1.4 to $1.7 billion (in 2010 dollars). The cost differential between the Draft EIS/EIR Baseline Alternative and the other route options is attributable to several factors, the most significant of which is the inclusion of below-grade segments. The length of the new Washington Boulevard Alternative is about 8.8 miles, of which one-third of the alignment could be an underground segment along Atlantic Boulevard in unincorporated East Los Angeles and then along Smithway Street in the City of Commerce. The cost of the underground segment would include elements such as underground stations and right-of-way acquisition near portal construction sites. Other factors include inflation adjustments and higher LRT construction costs in Los Angeles County, per recent construction bid prices reflecting more current market conditions. For these reasons, the cost of the Atlantic Underground Option is higher than those of the original Draft EIS/EIR Baseline Alternative.
SR 60 and Washington Blvd ‘Combined’ Operations
Measure M funding for the Eastside Phase 2 project includes a total of $6 billion, of which $3 billion is not identified to be available until after 2052. Initial funds to start construction of the initial segment of the project are currently scheduled to commence in 2029. Based on preliminary cost estimates, the total commitment of $6 billion could be enough to cover the cost of both alternatives. The Technical Study explored the feasibility of operating both alternatives (SR 60 and Washington Boulevard), and it has been determined that operating both segments is feasible, but would require infrastructure and operational elements that would not be required if only one or the other alternative were operated as a ‘stand-alone’ line.
If both the SR 60 and Washington segments were built, there would only be one maintenance facility needed to service rail vehicles operating on both lines. The exact location of the maintenance facility will be determined in the next phase of work. In order to move all Eastside 2 trains serving both branches to that maintenance facility, a potential three-way junction concept (similar to the planned operations at the Crenshaw Line/Green Line merge junction) would be needed. The provision of a three-way junction, potentially underground, would allow patrons to travel to points along either the SR 60 branch or the Washington branch, therefore offering greater connectivity with the project area and to/from the greater Los Angeles region. Another benefit of a three-way junction is that it could support a third line from South El Monte to Whittier, potentially allowing for 5-minute service on each branch.
Based on the analysis performed, a ‘Combined’ Alternative, which includes both the SR 60 and Washington Boulevard segments, has sufficient technical merit to be included as a new Alternative in the updated Project Definition. The inclusion of a Combined Alternative in the re-initiated environmental process would be the only way to environmentally clear the three-way underground junction, which would not be needed if only SR 60 or Washington were built. In the next phase, the Eastside Phase 2 project team would develop and advance the design of a three-way junction, define the associated operating plan and determine its physical footprint.
Community Outreach
The study team undertook an extensive outreach effort with numerous project stakeholders throughout the study area to provide project updates, receive feedback on the north-south connection options development process and seek feedback on the overall community engagement strategy. Over 110 outreach meetings were held during the course of the technical study, including:
• 10 community meetings (including East Los Angeles (3 meetings), Whittier (2 meetings), Montebello (2 meetings), South El Monte (2 meetings), and Commerce (1 meeting)
• 30 briefings with SR 60 Coalition and Washington Boulevard Coalition, both on monthly basis
• 70 stakeholder briefings with East Los Angeles residents, businesses, neighborhood and community groups, local city staff or city council members, federal and state elected officials, chambers and business associations, major property owners/developers, Councils of Government and Service Councils in the San Gabriel Valley and Gateway Cities.
• Two tours of Metro maintenance facilities in Santa Monica and Monrovia
Of the 10 community meetings held, five were recently completed in early-mid February 2017 in the communities of Whittier, Montebello, South El Monte, City of Commerce, and East Los Angeles. A total of 318 persons attended the five meetings, and provided a valuable opportunity to receive critical feedback on Technical Study findings and recommendations. In general, there is strong support for the Eastside Phase 2 project and re-initiation of the environmental process, based on the recommended Project Definition.
Several key areas of consensus and themes emerged based on survey results and comments made. First, there was strong support expressed for the Atlantic Underground Option as the new Washington Boulevard Alternative. Of 235 respondents surveyed at the February 2017 community meetings, 63% agreed that the Atlantic Underground Option has sufficient merit to be recommended as the new Washington Boulevard Alternative. This result was strongly corroborated by sentiments expressed at the Community Meetings, particularly from attendees who made comments at the East Los Angeles meeting on February 16. Second, there was openness to studying the ‘Combined’ Alternative in the next phase of work, as evidenced by the 50% of respondents who felt that the ‘Combined’ Alternative had enough merit to study in the next phase plus an additional 16% of the respondents who expressed the ‘Combined’ Alternative maybe have some merit to be further studied.
There was also support for SR 60 NSDV Alternative, which several attendees felt could serve a robust east-west commuter market and has lesser impacts to residential community/businesses during and after construction. While there is strong support for the Eastside Phase 2 project overall, participants shared concerns regarding the potential impacts during the construction, especially as it relates to traffic and business disruption and/or relocation. Participants also highlighted the importance of designing the stations with ease of access for pedestrians, bike riders and park and ride.
The study team has received positive feedback from the key stakeholders indicating their general support of the technical study findings and recommendations. Through April 2017, the study team will continue to provide briefings with study area stakeholder groups. A complete report of all outreach activities will be provided at Metro committee meetings as requested.
Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT
This Board action will not have any adverse safety impacts on Metro’s employees and patrons.
Financial_Impact
FINANCIAL IMPACT
The FY 2017 budget includes $1,990,600 for Professional Services in Cost Center 4350, Project 460232 (Eastside Transit Corridor Phase 2). Since this is a multi-year program, the Cost Center Manager and Chief Planning Officer will be responsible for budgeting in future years.
Impact to Budget
The source of funds is Repayment of Capital Project Loans Fund 3562. These funds are eligible for bus and/or rail operating and capital expenses.
Alternatives_Considered
ALTERNATIVES CONSIDERED
The Board could choose to direct staff to proceed with environmental clearance for only one of the two alternative routes that have been studied in the Technical Study. This is not recommended as it could preclude future opportunities to connect both the northern (Route 60) and southern (Washington Boulevard) branches of this corridor.
Next_Steps
NEXT STEPS
Upon approval, staff will procure professional services to prepare a revised draft environmental document and conduct advanced conceptual engineering through final environmental clearance. Upon completion of procurement, staff will return to the Board to seek approval on the negotiated contract budget amounts for the aforementioned professional services.
Attachments
ATTACHMENTS
Attachment A - July Board Motion
Attachment B - Project Schedule
Attachment C - Map of North/South Route Options for Washington Boulevard
Attachment D - Eastside Phase 2 Route Options Screening Analysis and Community Outreach Executive Summary
Prepared_by
Prepared by: Jill Y. Liu, Transportation Planning Manager, Countywide Planning & Development, (213) 922-7220,
Eugene Kim, Deputy Executive Officer, Countywide Planning & Development, (213) 922-3080,
David Mieger, Interim Senior Executive Officer, Countywide Planning & Development, (213) 922-3040
Approved_by
Approved by: Therese W. McMillan, Chief Planning Officer, (213) 922-7077