Subject/Action
SUBJECT: ALL TRANSIT CORRIDOR AND CAPITAL PROJECTS
ACTION: APPROVE CONTRACT MODIFICATION
Heading
RECOMMENDATION
Title
INCREASE the authorized funding for Contract No. EN077 with Arcadis US, Inc. (AUS), to fund additional Environmental Hazardous Materials and Construction Services Task Orders in an amount not-to-exceed $3,255,000 increasing the total Contract Value from $38,000,000 to $41,255,000.
Rationale
RATIONALE
In September 2011, the Board authorized negotiation and award, and the Board funded the Contract in the initial amount of $38,000,000, based upon a staff cost estimate of work necessary to support Metro’s approved Capital Construction Program for FY12 through FY16. Outstanding Task Orders that were awarded in FY16 were carried over to FY17. These Task Orders are scheduled to terminate with the expiration of the EN077 Contract at the end of FY17. Any remaining Contract Value was projected to be sufficient to support existing environmental services efforts.
The emergence of changed conditions at major capital projects including Location 61S as well as multiple notices of violations resulting from additional regulatory compliance requirements related to State Water Resources Control Board and City and County of Los Angeles Fire Department underground storage tank requirements and SB 989 regulations required the additional use of AUS services beyond what staff has anticipated that can be handled within the current AUS Contract Value. Based upon forecasted work for the remainder of FY17 up to and until the expiration of this Contract at the end of the FY17, staff is requesting additional funding in the amount of 3,255,000 which would bring the total authorized value for this Contract to $41,255,000.
Nearly every capital project, and many ongoing facilities maintenance or restoration activities undertaken by Metro require evaluation and, as necessary, removal or treatment of hazardous or contaminating substances. Metro must comply with all environmental laws to avoid fines, and civil or criminal liability. To ensure such compliance, Metro has solicited and awarded contracts for environmental services. Under Contract No. EN077, AUS assists with the proper clean up, abating, managing, transporting, and disposing of contaminated or hazardous materials at various Metro operating facilities; and sampling and testing at various locations for contaminated and hazardous soils and water. AUS also performs, under this Contract, construction services that require environmental contractor specialization.
Specific projects identified to require environmental services, along with estimated costs of these services, is shown below. Attachment A includes a month to month cashflow projection on when these expenditures are going to be spent.
Underground Storage Tank Program Est. Cost
Division 2 EG UST Removal & AST Install $350,000
Division 5 UST/AST Repairs and Upgrades $600,000
Division 9 UST Repairs and Upgrades $550,000
Division 10 UST System Repair $300,000
Emergency response failures UST/AST $135,260
Other Projects
Soil & Water Transportation and Disposal $100,000
Purple Line Extension Waste Soil $ 40,000
Patsaouras Plaza Busway Management Environmental Support $217,000
Location 61 S / Soil Remediation $237,000
Regional Connector Waste Management On Call $ 15,000
PLE Lead and Asbestos Abatement Section 2 $250,000
Crenshaw - LAX On-Call Incident Response Service $ 45,000
Location 61S Phase II Excavation $600,000
Bob Hope Airport Station $ 45,000
Geotechnical Waste Removal / LinkUSA Project Support $ 70,000
TOTAL $3,554,260
As of November 2016 (the time of report preparation), there is approximately $1,900,000 remaining in the Contract Value for AUS. The requested increase in Contract Value will allow for the completion of the remaining work scheduled for FY17.
A replacement Environmental Services contract is currently under procurement and upon award at the end of FY17 will replace AUS to perform Environmental Services work.
Impacts to other contracts
IMPACTS TO OTHER CONTRACTS
Timely and thorough environmental services in connection with other construction contracts is essential to complete capital projects within schedule and budget. If the value of Contract No. EN077 is not increased, staff will not be able to respond to the outstanding and newly identified compliance requirements (including those that address the notices of violations); as well as respond to the major capital project changed conditions. Staff will also have to delay any remediation work that has a direct impact on the succeeding phases of projects. There is already a procurement for a replacement contract but the award will not be until the later part of this fiscal year. Any delay in provision of environmental support will significantly increase Metro’s liability for environmental regulatory compliance and contractor monetary claims of delay.
Financial_Impact
FINANCIAL IMPACT
EN077 is an Indefinite Delivery/Indefinite Quantity (IDIQ) contract. No Metro funds are obligated until a Contract Work Order (CWO) is issued by a Metro authorized Contracting Officer against a valid project budget. No expenditures are authorized until a Task Order is awarded by a Metro authorized Contracting Officer for a specific package of work within the CWO.
To date, Metro’s financial and change control systems indicate that approximately $36,000,000 out of the previously Board-approved $38,000,000 has been obligated for completed and ongoing work. The remaining balance would not be sufficient to support contractor efforts to complete the required work for the rest of FY17.
The additional funding of $3,255,000 is an increase in the amount which may be obligated and spent under the Contract. This increase in Contract Value is anticipated to be all spent by the end of FY17 and by the time the EN077 replacement contract is awarded.
Obligations and authorizations made within the total Contract Value will be against specific project or operations budgets which make up the Board-approved Metro budget for any particular fiscal year. The Chiefs of each of the business units overseeing these projects and the respective project managers are responsible for budgeting the costs.
Impact to Bus and Rail Operating and Capital Budget
The funding for this Contract Modification will come from various sources of projects and their corresponding funds (see Attachment A). These funds are eligible for bus and rail operating and capital expenditures.
Alternatives_Considered
ALTERNATIVES CONSIDERED
The Metro Board of Directors could decide not to increase the Contract Value for this Contract and thus staff has to solicit and award individual contracts for each environmental task to ensure the regulatory requirements and required mitigation work at project sites are addressed. Staff does not recommend this alternative owing most importantly to delays and correspondingly to high costs; as well as the administrative inefficiencies for managing multiple contracts.
As another alternative, Metro could perform all the environmental hazardous materials and construction services in-house. However to do so, Metro would need to hire additional staff with expertise in many different subjects, such as drilling, laboratory science, and operating heavy earth-moving and material handling equipment, as well as purchase earthmoving and material handling equipment, and laboratory equipment. Staff does not recommend this alternative owing to high capital costs to procure personnel and equipment as well as potential for implementation and training delays.
Next_Steps
NEXT STEPS
After the recommended Board Action is approved, staff will complete the process to award task orders to address newly identified and required regulatory actions and mitigation/remediation measures.
Attachments
ATTACHMENTS
Attachment A - Procurement Summary
Attachment B - Contract Modification/Change Order Log
Attachment C - DEOD Summary
Attachment D - Summary of Current and Proposed Work Requiring AUS Services
Prepared_by
Prepared by:
Cris B. Liban, Executive Officer, Environmental Compliance and Sustainability
(213) 922-2471
Tom Kefalas, Sr. Manager, Environmental Compliance and Services (213) 922-4887
Reviewed_By
Reviewed by:
Richard Clarke, Chief Program Management Officer (213) 922-7557
Debra Avila, Chief Vendor/Contract Management Officer (213) 418-3051