File #: 2018-0069   
Type: Contract Status: Agenda Ready
File created: 2/23/2018 In control: Operations, Safety, and Customer Experience Committee
On agenda: 7/19/2018 Final action:
Title: AUTHORIZE the Chief Executive Officer to award a 60-month, indefinite delivery indefinite quantity Contract No. OP36847000 to Tristar Power Solutions LLC, the lowest responsive and responsible bidder for Metro Red Line (MRL) Uninterruptible Power Supplies for a total not to exceed amount of $1,004,000 inclusive of sales tax and subject to resolution of protest(s), if any.
Sponsors: System Safety, Security and Operations Committee
Indexes: B Line (Red) Segment 3, Budgeting, Contracts, Maintenance, Metro Purple Line, Metro Rail A Line, Metro Rail B Line, Metro Rail D Line, Metro Red Line, Procurement, Red Line MOS-2 North, Red Line MOS-2 West, Replacement Of Ups/Batteries On Red Line Fy17-Fy22 (Project), Safety, Supervisory Control And Data Acquisition
Attachments: 1. Attachment A - Expenditure Plan CP205106, 2. Attachment B - Procurement Summary, 3. Attachment C - DEOD Summary
Related files: 2018-0502
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

OPERATIONS, SAFETY AND CUSTOMER EXPERIENCE COMMITTEE

JULY 19, 2018

 

Subject

SUBJECT:                     METRO RED LINE UNINTERRUPTIBLE POWER

SUPPLY (UPS)

 

Action

ACTION:                     AWARD CONTRACT

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to award a 60-month, indefinite delivery indefinite quantity Contract No. OP36847000 to Tristar Power Solutions LLC, the lowest responsive and responsible bidder for Metro Red Line (MRL) Uninterruptible Power Supplies for a total not to exceed amount of $1,004,000 inclusive of sales tax and subject to resolution of protest(s), if any.

 

Issue

ISSUE

 

This procurement replaces old defective, unreliable Uninterruptible Power Supply (UPS) units on Metro Red Line (MRL) Segments 2 and 3 that have reached the end of their useful service life.  The performance of these UPS’s has become unreliable as these units are more than 18 years old.  The Original Equipment Manufacturer has stopped providing spare parts to support maintenance of the obsolete units.

 

Discussion

DISCUSSION

 

Three stations of MRL Segment 2 opened in 1996 and the other five stations were completed in 1999 while Segment 3 opened in 2000. In total, the Metro Red Line rail service has sixteen passenger stations and two (2) facilities underground. These two segments have twenty-five (25) Uninterruptible Power Supplies (UPS) in service requiring replacement. The operation of these UPS’s is for critical Fire and Life Safety functions.

 

The UPS equipment must be available to provide Emergency Power for lighting and Communication Systems to support evacuation of patrons and employees when normal utility power to the underground passenger stations and facilities is loss. In addition, these UPS’s provide back-up to Metro’s underground fire alarm system.

 

The Diversity and Economic Opportunity Department (DEOD) did not recommend a Small Business Enterprise (SBE)/Disabled Veteran Business Enterprise (DVBE) goal for this solicitation.  The prime would provide replacement of Uninterruptible Power Supply (UPS) parts, and ship to Metro. Metro will be responsible for installation. 

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

The UPS is required for the proper functioning of critical emergency lighting for tunnels and passenger station evacuations. UPS’s provide electrical power to operate Police and Metro radio and communication systems, Variable Message Signs and Supervisory Control and Data Acquisition systems (SCADA).  UPS’s are required for the control power to operate substation High Voltage Switchgears.

 

Financial_Impact

FINANCIAL IMPACT

 

The total five year contract amount is $1,004,000. FY18 funding of $266,600 is included in  cost center 3960, Traction Power under project 205106, MRL UPS/Battery Replacement.  FY19 funding is $833,000. The Life-of-Project Budget for CP 205106 is $3,684,000 and inception-to-date there is $13,019 in expenditures charged against this project.

 

Since this is a multi-year contract, the  Senior Executive Officer, Maintenance and Engineering and cost center manager will ensure that the balance of funds are budgeted in future Fiscal Years.

 

Impact to Budget

 

The current source of funds for this procurement is Proposition C 40% Discretionary.   This funding source maximizes the allowable fund use given approved funding provisions.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

There are no suitable energy sources for the replacement of emergency UPS’s to operate the critical emergency loads.

 

Next_Steps

NEXT STEPS

 

Upon Board approval, staff will execute Contract No. OP36847000 to Tristar Power Solutions LLC to provide Metro Red Line Uninterruptible Power Supplies, develop a schedule for the replacement of the UPS units at a rate of one unit every two (2) months, and select and form a construction crew dedicated to plan the replacement of the old defective unit with minimum or no disruption to critical system it supplies.

 

Attachments

ATTACHMENTS

 

Attachment A - Expenditure Plan 

Attachment B - Procurement Summary

Attachment C - DEOD Summary

 

Prepared_by

Prepared by:                      Winston Dixon, Manager, Wayside Systems (213) 272-8229

Errol Taylor, Senior Executive Officer, Maintenance and Engineering, (213) 922-3227

 

Reviewed_By

Reviewed by:                      James T. Gallagher, Chief Operations Officer, (213) 418-3108

Debra Avila, Chief, Vendor/Contract Management Officer, (213) 418-3051