File #: 2017-0138   
Type: Contract Status: Passed
File created: 3/1/2017 In control: Construction Committee
On agenda: 4/20/2017 Final action: 4/27/2017
Title: AUTHORIZE the Chief Executive Officer (CEO) to execute a Modification to Contract No. C1043 with Griffith Company, for the design and construction of the Universal City Pedestrian Bridge, in the amount of $450,000, increasing the total current contract value from $24,264,752 to $24,714,752 within the Life of Project budget.
Sponsors: Construction Committee
Indexes: Budget, Budgeting, Construction, Contracts, Design build, Metro Rail B Line, Metro Red Line, Pedestrians, Procurement, Proposition A, Universalcity Station Pedestrian Bridge (Project)
Attachments: 1. Attachment A - Procurement Summary.pdf, 2. Attachment B - Contract Modification Change Order Log.pdf, 3. Attachment C - DEOD Summary.pdf

Meeting_Body

CONSTRUCTION COMMITTEE

APRIL 20, 2017

 

Subject/Action

SUBJECT:                     UNIVERSAL CITY PEDESTRIAN BRIDGE

 

ACTION:                     AUTHORIZATION FOR CONTRACT MODIFICATION

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer (CEO) to execute a Modification to Contract No. C1043 with Griffith Company, for the design and construction of the Universal City Pedestrian Bridge, in the amount of $450,000, increasing the total current contract value from $24,264,752 to $24,714,752 within the Life of Project budget.

 

Issue

ISSUE

 

This action represents staff’s efforts through negotiations to settle all claims.  Staff is requesting approval to execute this final Contract Modification because the current available CMA is not sufficient to take action within staff authority.  This Contract Modification is required to close-out the contract, and does not affect the Life of Project (LOP) budget. 

Discussion

DISCUSSION

 

 

Findings

 

Metro issued the Notice to Proceed (NTP) for Design-Build (DB) Contract No. C1043 for the Universal City Pedestrian Bridge on January 9, 2014.  The bridge had an aggressive schedule and was opened to the public on April 7, 2016.

 

During the course of construction, the contractor requested several design and construction changes.  This Modification includes additional costs for escalators, increased elevator framing, and design modifications due to easement constraints.

 

Considerations

 

Staff has evaluated the merit of the requested changes and has followed Metro processes and procedures to validate and negotiate the change request.  A list of executed (approved) and unexecuted (pending) modifications is included in Attachment B.

There is no change in the approved LOP amount of $29,585,000.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

This recommended action has no impact on safety.

Financial_Impact

FINANCIAL IMPACT

 

The FY17 adopted budget of $2,078,000 for the Universal Pedestrian Bridge, project 809382, in Cost Center 8510 includes the $450,000 required for this board action.  With the approval of this action, staff will no longer need to budget for the construction contract in FY18. 

Impact to Budget

 

The source of funds for this project is Prop A 35%. Prop A 35% funds are eligible for rail operations.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may choose not to approve the Modification. This alternative is not recommended, as staff would be unable to close out the project.  

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - Contract Modification/Change Order Log

Attachment C - DEOD Summary

 

Prepared_by

Prepared by:                      

 

Milind Joshi, Sr. Director, Project Engineering, (213) 922-7985

Brad Owen, Deputy Executive Officer, Construction Management, (213) 922-7384

Tim Lindholm, Executive Officer, Capital Projects (213) 922-7297

 

 

Reviewed_By

Reviewed by:                      

 

Debra Avila, Chief Vendor/Contract Management Officer, (213) 418-3051

Richard Clarke, Chief Program Management Officer, (213) 922-7557