Meeting_Body
CONSTRUCTION COMMITTEE
JULY 18, 2019
Subject
SUBJECT: OFFICE OF THE INSPECTOR GENERAL CHANGE ORDER/MODIFICATION CONSTRUCTION SPOT CHECKS
Action
ACTION: RECEIVE AND FILE
Heading
RECOMMENDATION
Title
RECEIVE AND FILE Office of the Inspector General Change Order/Modification Construction Spot Check Report.
Issue
ISSUE
On January 25, 2018, the Metro Board directed the Office of the Inspector General ("OIG") to conduct random spot checks on the projects listed in the quarterly program management report to ensure that the delegation of authority to approve construction Change Orders policy is performing in the manner desired by the Board of Directors.
Background
BACKGROUND
This quarters OIG's Spot Check Program ("Spot Checks) focuses on approved Change Orders and Modifications that exceed $500,000 dollars. The four Change Orders in this report were selected from the July 2019 Program Management Major Project Status Report (File # 2019-0494), covering March 1 to May 31 2019. The information for the Spot Checks was collected from the Program Management Information System (PMIS) which is the department's database system. Also, in-person and telephonic interviews were conducted with Metro Program Management, Project Control, and Procurement staff from each individual project office.
We found that all four of the Change Orders in this report were negotiated and executed more expeditiously than would have occurred pursuant to the former Board approval process, and all four were approved faster with the new delegation of authority. In addition all four Change Orders were negotiated at lower cost than the contractors' proposed price. This quarter's Spot Checks of Change Orders/Modifications found the delegation of authority has resulted in:
* A negotiated amount that was reasonable for the work to be done,
* Enabled the contractor to immediately order parts and materials, reducing delay.
* Consultant having no overlap in schedule and was ...
Click here for full text