A. AWARDING AND EXECUTING up to a 60-month, firm fixed price Contract No. AE97976000 to Vermont Corridor Partners Joint Venture, a joint venture between AECOM Technical Services, Inc., Terry A. Hayes Associates, Inc., and RAW International, Inc., in the amount of $55,668,537, to prepare the Planning and Environmental Study for the Vermont Transit Corridor, subject to resolution of any properly submitted protest(s), if any, and;
B. AUTHORIZING the CEO to execute individual Contract Modifications within the Board-approved Contract Modification Authority.?
Issue
ISSUE
The Vermont Transit Corridor is a Measure M project with a projected opening date within Fiscal Years (FY) 2028 to 2030. Currently, there is $425 million (2015$) allocated for this project. To advance the project in accordance with the Measure M schedule, a Locally Preferred Alternative (LPA) needs to be identified and environmentally cleared.
On February 6, 2023, Metro issued a Request for Proposal (RFP No. AE97976) seeking a qualified consultant for planning, environmental, and engineering services for the Vermont Transit Corridor Project (Project). Board approval is needed to award Contract No. AE97976000 to allow the consultant to begin work.
Background
BACKGROUND
Vermont Avenue is the second busiest transit corridor in Los Angeles County with nearly 71,000 daily boardings (pre-Covid) served by Metro Local Line 204 and Metro Rapid Line 754, as well as the Metro B, D, E, and C rail lines. The corridor also connects some of the region's most economically and socially diverse communities. Between Hollywood Boulevard and 120th Street (Attachment A), 100% of the Vermont corridor is contained within Metro Equity-Focus Communities. The Vermont Transit Corridor Project will not only improve ...