File #: 2016-0101   
Type: Contract Status: Filed
File created: 2/1/2016 In control: Construction Committee
On agenda: 5/19/2016 Final action: 5/26/2016
Title: AUTHORIZE the Chief Executive Officer to execute: A. Modification No. 3 to Contract No. PS8610-2879, with Hill International, Inc. for Program Control Management and Support Services, to exercise the final one-year option thereby extending the period of performance from June 28, 2016 to June 28, 2017, and increase the total contract not-to-exceed amount $6,210,946 from $18,482,598 to $24,693,544; and B. individual Contract Work Orders (CWOs) and Contract Modifications within the Board approved not-to-exceed contract value.
Indexes: Budget, Budgeting, Capital Project, Construction, Construction Support, Contractors, Contracts, Labor, Metro Purple Line, Metro Rail D Line, Procurement, Program, Program management, Project, Project management, Request For Proposal, Westside Subway Extension/Purple Line Extension Phase 1, Westside Subway Extension/Purple Line Extension Phase 2
Attachments: 1. Attachment A - Procurement Summary PCMS, 2. Attachment B - Contract Work Order and Modification Log PCMS, 3. Attachment C - DEOD Summary PCMS
Meeting_Body
CONSTRUCTION COMMITTEE
MAY 19, 2016


Subject/Action
SUBJECT: PROGRAM CONTROL MANAGEMENT AND SUPPORT SERVICES

ACTION: EXERCISE CONTRACT OPTION AND AUTHORIZE ADDITIONAL CONTRACT VALUE IN AN AMOUNT NOT TO EXCEED $6,210,946

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to execute:

A. Modification No. 3 to Contract No. PS8610-2879, with Hill International, Inc. for Program Control Management and Support Services, to exercise the final one-year option thereby extending the period of performance from June 28, 2016 to June 28, 2017, and increase the total contract not-to-exceed amount $6,210,946 from $18,482,598 to $24,693,544; and

B. individual Contract Work Orders (CWOs) and Contract Modifications within the Board approved not-to-exceed contract value.

Issue
ISSUE

On May 24, 2012, the Board authorized the Chief Executive Officer to award a five-year labor-contract to provide Program Control Management and Support Services (PCMS) to support Board adopted capital projects. The Board also authorized individual CWOs be executed for an amount not to exceed $16,071,824 plus a 15% ($2,410,774) contract modification authority of the contract award, for a total not to exceed $18,482,598.

Contract No. PS8610-2879 was executed on June 28, 2012 for a three-year base term plus two one-year options. Since contract inception, Hill International has been responsive in providing the PCMS services to support Metro projects. Primarily due to satisfactorily performance, the first one-year option was exercised, extending the period of performance through June 28, 2016, without any increase to the approved contract value.

Staff has issued CWOs and modifications totaling $17,407,044 to date. Staff is requesting an increase to continue PCMS required to support Metro adopted capital projects through the final option-year period. It has been determined that the previously negotiated rates for the final year with Hill International ar...

Click here for full text