File #: 2017-0138   
Type: Contract Status: Passed
File created: 3/1/2017 In control: Construction Committee
On agenda: 4/20/2017 Final action: 4/27/2017
Title: AUTHORIZE the Chief Executive Officer (CEO) to execute a Modification to Contract No. C1043 with Griffith Company, for the design and construction of the Universal City Pedestrian Bridge, in the amount of $450,000, increasing the total current contract value from $24,264,752 to $24,714,752 within the Life of Project budget.
Sponsors: Construction Committee
Indexes: Budget, Budgeting, Construction, Contracts, Design build, Metro Rail B Line, Metro Red Line, Pedestrians, Procurement, Proposition A, Universalcity Station Pedestrian Bridge (Project)
Attachments: 1. Attachment A - Procurement Summary.pdf, 2. Attachment B - Contract Modification Change Order Log.pdf, 3. Attachment C - DEOD Summary.pdf
Meeting_Body
CONSTRUCTION COMMITTEE
APRIL 20, 2017

Subject/Action
SUBJECT: UNIVERSAL CITY PEDESTRIAN BRIDGE

ACTION: AUTHORIZATION FOR CONTRACT MODIFICATION

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer (CEO) to execute a Modification to Contract No. C1043 with Griffith Company, for the design and construction of the Universal City Pedestrian Bridge, in the amount of $450,000, increasing the total current contract value from $24,264,752 to $24,714,752 within the Life of Project budget.

Issue
ISSUE

This action represents staff's efforts through negotiations to settle all claims. Staff is requesting approval to execute this final Contract Modification because the current available CMA is not sufficient to take action within staff authority. This Contract Modification is required to close-out the contract, and does not affect the Life of Project (LOP) budget.
Discussion
DISCUSSION


Findings

Metro issued the Notice to Proceed (NTP) for Design-Build (DB) Contract No. C1043 for the Universal City Pedestrian Bridge on January 9, 2014. The bridge had an aggressive schedule and was opened to the public on April 7, 2016.

During the course of construction, the contractor requested several design and construction changes. This Modification includes additional costs for escalators, increased elevator framing, and design modifications due to easement constraints.

Considerations

Staff has evaluated the merit of the requested changes and has followed Metro processes and procedures to validate and negotiate the change request. A list of executed (approved) and unexecuted (pending) modifications is included in Attachment B.
There is no change in the approved LOP amount of $29,585,000.

Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT

This recommended action has no impact on safety.
Financial_Impact
FINANCIAL IMPACT

The FY17 adopted budget of $2,078,000 for the Universal Pedestrian Bridge, project 809382, in Cost ...