File #: 2016-0623   
Type: Contract Status: Passed
File created: 8/9/2016 In control: Construction Committee
On agenda: 8/18/2016 Final action: 8/25/2016
Title: AUTHORIZE Contract Modification No. 184 by Caltrans for construction contract of the Segment 4 of the I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) under the Funding Agreement No. MOU.P0008355/8501 A/A6, in the amount of $1,219,548.11.
Indexes: Budgeting, Congestion Mitigation And Air Quality Improvement Program, Construction, Contractors, Contracts, High occupancy vehicle lanes, I-5 North County Capacity Enhancements, Program, Project, SR-118, SR-134
Meeting_Body
REVISED
CONSTRUCTION COMMITTEE
AUGUST 18, 2016

Subject/Action
SUBJECT: I-5 NORTH CAPACITY ENHANCEMENTS FROM SR-134 TO SR-118 (FUNDING AGREEMENT NO. MOU.P0008355/8501 A/A6)

ACTION: AUTHORIZE CONTRACT MODIFICATION

Heading
RECOMMENDATION

Title
AUTHORIZE Contract Modification No. 184 by Caltrans for construction contract of the Segment 4 of the I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) under the Funding Agreement No. MOU.P0008355/8501 A/A6, in the amount of $1,219,548.11.

Issue
ISSUE

The I-5 North Capacity Enhancement Project includes freeway widening and construction of HOV lanes and other improvements between SR-134 and SR-118. The project is divided into four segments. Segment 4 is between SR-134 and Magnolia Street. The total Project budget for Segment 4 is $106,756,000 of which $68,956,000 is federal funds (RSTP and CMAQ) and $37,800,000 is local Prop C and Measure R funds. CMAQ funds are programmed through Metro.

The State of California, Department of Transportation (Caltrans) owns, designed, and is managing construction of the Project. The original steel girder fabrication window for Providencia Bridge had a scheduled start date of October 4, 2011, which was delayed due to survey and design issues leading to the contractor's inability to fabricate the girders.

In May 2016, Metro Highway Program staff worked closely with Caltrans and its Contractor to reach a resolution wherein the Contractor committed to expedite the fabrication of girders with an estimated schedule saving of 11 months, moving the date of completion of the Project up from May 31, 2019 to June 29, 2018. The negotiated cost of the Contract Modification No.184 is $1,219,548.11. If this Contract Modification is not approved, delay would result in $4,019,200 in expenditures through completion of the project. This Contract Modification will save a net of $2,799,652. Contract modifications exceeding $500,000 require Board auth...

Click here for full text