File #: 2016-0980   
Type: Agreement Status: Non-Calendar
File created: 12/13/2016 In control: Board of Directors - Regular Board Meeting
On agenda: 1/26/2017 Final action: 1/26/2017
Title: CONSIDER: A. AUTHORIZING the Chief Executive Officer (CEO) to negotiate and execute contract modification(s) to Contract No. C0988 with Walsh/Shea Corridor Constructors (WSCC), for final costs associated with construction on accommodations so as not to preclude a future Light Rail Transit (LRT) Station at 96th Street and implement an agreement on critical cost and schedule impacts in an amount of $59,150,000 increasing the total contract value from $1,311,627,532 to $1,370,777,532, no impact to Crenshaw/LAX Project Life-of-Project Budget; B. AMENDING the FY17 budget by $28,600,000 for Project 460303 Airport Metro Connector Accommodations from $10,760,760 to $39,360,760 for the allocable portion of its costs related to the $59,150,000 under Recommendation A; and C. AUTHORIZING the CEO for a pilot period of 1 year to negotiate and execute project-related agreements, including contract modification(s) up to the authorized Life-of-Project budget, to streamline project management of the...
Sponsors: Construction Committee
Indexes: Budget, Budgeting, Construction, Construction management, Contracts, Crenshaw/LAX Transit Corridor Project, Funding plan, Los Angeles International Airport, Measure R, Metro Crenshaw Line, Metro Exposition Line, Metro Rail E Line, Payment, Procurement, Program management, Project, Project management, Safety
Attachments: 1. Attachment A - Procurement Summary.pdf, 2. Attachment B - Contract Modification-Change Order Log.pdf, 3. Attachment C - DEOD Summary.pdf, 4. Attachment D - WSCC-Metro Agreement.pdf, 5. Attachment E - WSCC-Metro Agreement.pdf
REVISED
PLANNING AND PROGRAMMING COMMITTEE
JANUARY 18, 2017
CONSTRUCTION COMMITTEE
JANUARY 19, 2017



Subject/Action
SUBJECT: CRENSHAW/LAX TRANSIT PROJECT AND AIRPORT METRO CONNECTOR ACCOMMODATIONS

ACTION: APPROVE CONTRACT MODIFICATION FOR 96TH STREET ACCOMMODATIONS AND COST/SCHEDULE IMPACTS AGREEMENT


Heading
RECOMMENDATION

Title
CONSIDER:

A. AUTHORIZING the Chief Executive Officer (CEO) to negotiate and execute contract modification(s) to Contract No. C0988 with Walsh/Shea Corridor Constructors (WSCC), for final costs associated with construction on accommodations so as not to preclude a future Light Rail Transit (LRT) Station at 96th Street and implement an agreement on critical cost and schedule impacts in an amount of $59,150,000 increasing the total contract value from $1,311,627,532 to $1,370,777,532, no impact to Crenshaw/LAX Project Life-of-Project Budget;

B. AMENDING the FY17 budget by $28,600,000 for Project 460303 Airport Metro Connector Accommodations from $10,760,760 to $39,360,760 for the allocable portion of its costs related to the $59,150,000 under Recommendation A; and

C. AUTHORIZING the CEO for a pilot period of 1 year to negotiate and execute project-related agreements, including contract modification(s) up to the authorized Life-of-Project budget, to streamline project management of the Crenshaw/LAX Transit Project subject to monthly reporting requirements, that would include any pending project-related agreements, change orders/contract modifications and any significant changes to contract contingency to the Board of Directors. This action would allow the board to see in advance all project-related agreements and change orders.

Issue
ISSUE

WSCC commenced construction of the accommodations so as not to preclude a future LRT Station at 96th Street in July 2016. Metro and WSCC have completed negotiations for the direct, indirect and delay impact costs associated with the Crenshaw/LAX Transit Project constructing the accommodat...