REVISED
PLANNING AND PROGRAMMING COMMITTEE
JANUARY 18, 2017
CONSTRUCTION COMMITTEE
JANUARY 19, 2017
Subject/Action
SUBJECT: CRENSHAW/LAX TRANSIT PROJECT AND AIRPORT METRO CONNECTOR ACCOMMODATIONS
ACTION: APPROVE CONTRACT MODIFICATION FOR 96TH STREET ACCOMMODATIONS AND COST/SCHEDULE IMPACTS AGREEMENT
Heading
RECOMMENDATION
Title
CONSIDER:
A. AUTHORIZING the Chief Executive Officer (CEO) to negotiate and execute contract modification(s) to Contract No. C0988 with Walsh/Shea Corridor Constructors (WSCC), for final costs associated with construction on accommodations so as not to preclude a future Light Rail Transit (LRT) Station at 96th Street and implement an agreement on critical cost and schedule impacts in an amount of $59,150,000 increasing the total contract value from $1,311,627,532 to $1,370,777,532, no impact to Crenshaw/LAX Project Life-of-Project Budget;
B. AMENDING the FY17 budget by $28,600,000 for Project 460303 Airport Metro Connector Accommodations from $10,760,760 to $39,360,760 for the allocable portion of its costs related to the $59,150,000 under Recommendation A; and
C. AUTHORIZING the CEO for a pilot period of 1 year to negotiate and execute project-related agreements, including contract modification(s) up to the authorized Life-of-Project budget, to streamline project management of the Crenshaw/LAX Transit Project subject to monthly reporting requirements, that would include any pending project-related agreements, change orders/contract modifications and any significant changes to contract contingency to the Board of Directors. This action would allow the board to see in advance all project-related agreements and change orders.
Issue
ISSUE
WSCC commenced construction of the accommodations so as not to preclude a future LRT Station at 96th Street in July 2016. Metro and WSCC have completed negotiations for the direct, indirect and delay impact costs associated with the Crenshaw/LAX Transit Project constructing the accommodat...