File #: 2020-0132   
Type: Program Status: Agenda Ready
File created: 2/7/2020 In control: Planning and Programming Committee
On agenda: 3/18/2020 Final action:
Title: CONSIDER: A. APPROVING: 1. Deobligation of $4,226,964 previously approved Measure M Multi-Year Subregional Program (MSP) - Active Transportation Program, for re-allocation at the request of project sponsors, as shown in Attachment A; 2. Programming of additional $12,750,000 within the capacity of Measure M MSP - Transit Program, as shown in Attachment B; 3. Inter-program borrowing and programming of additional $4,350,143 from the Subregion's Measure M MSP - Active Transportation and Transit Programs to the Highway Efficiency Program, as shown in Attachment C; and B. AUTHORIZING the Chief Executive Officer or his designee to negotiate and execute all necessary agreements and/or amendments for approved projects.
Sponsors: Planning and Programming Committee
Indexes: Active Transporation, Transit And Tech Program - Expenditure Plan Line Item 56 (Project), Active Transportation Program, Agreements, Bicycling, Budgeting, Construction, Deobligation, Guidelines, Highway Efficiency Program, Highway Efficiency Program (North County) (Project), Joint Powers Agreement, Lake Los Angeles, Lancaster, Measure M, Measure M Multi-Year Subregional Program, Measure R, Metrolink, Metrolink Antelope Valley Line, Nonmotorized transportation, North Los Angeles County subregion, North Los Angeles County Transportation Coalition, Outreach, Palmdale, Pedestrians, Plan, Program, Project, Ridesourcing, Santa Clarita, SR-138, SR-14, Subsidies, Valencia
Attachments: 1. Attachment A - Active Transportation Project List, 2. Attachment B - Transit Program Project List, 3. Attachment C - Highway Efficiency Program Project List
Related files: 2020-0232
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

PLANNING AND PROGRAMMING COMMITTEE

MARCH 18, 2020

 

Subject

SUBJECT:                     MEASURE M MULTI-YEAR SUBREGIONAL PROGRAM ANNUAL UPDATE - NORTH COUNTY SUBREGION

 

Action

ACTION:                     APPROVE RECOMMENDATIONS

 

Heading

RECOMMENDATION

 

Title

CONSIDER:

 

A.                     APPROVING:

1.                     Deobligation of $4,226,964 previously approved Measure M Multi-Year Subregional Program (MSP) - Active Transportation Program, for re-allocation at the request of project sponsors, as shown in Attachment A;

2.                     Programming of additional $12,750,000 within the capacity of Measure M MSP - Transit Program, as shown in Attachment B;

3.                     Inter-program borrowing and programming of additional $4,350,143 from the Subregion’s Measure M MSP - Active Transportation and Transit Programs to the Highway Efficiency Program, as shown in Attachment C; and

 

B.                     AUTHORIZING the Chief Executive Officer or his designee to negotiate and execute all necessary agreements and/or amendments for approved projects.

 

Issue

ISSUE

 

Measure M MSPs are included in the Measure M Expenditure Plan.  All MSP funds are limited to capital projects.  The annual update approves additional eligible projects for funding and allows the North County Subregion and implementing agencies to revise scope of work, schedule, amend project budgets as well as removal of projects.  This update includes changes to projects which have received Board approval and funding allocation for new projects.  Funds are programmed through Fiscal Year (FY) 2022-23.  The Board’s approval is required to program additional funds and the updated project lists which serve as the basis for Metro to enter into agreements and/or amendments with the respective implementing agencies.

 

Discussion

DISCUSSION

 

In February 2019, the Metro Board of Directors approved North County Subregion’s first MSP Five-Year Plan and programmed funds in: 1) Measure M MSP - Active Transportation Program (expenditure line 52); 2) Measure M MSP - Transit Program (expenditure line 64); and 3) Measure M MSP - Highway Efficiency Program (expenditure line 81).

 

Metro staff continued working closely with the North County Transportation Coalition Joint Powers Authority (NCTC JPA) and the implementing agencies on project eligibility reviews of the proposed projects for this annual update.  Metro required, during staff review, a detailed project scope of work to confirm eligibility and establish the program nexus, i.e. project location and limits, length, elements, phase(s), total expenses and funding request, and schedule, etc.  This level of detail will ensure timeliness of the execution of the project Funding Agreements once the Metro Board approves the projects.  For those proposed projects that will have programming of funds in FY 2021-22 and beyond, Metro accepted high level (but focused and relevant) project scope of work during the review process.  Metro staff will work on the details with the NCTC JPA and the implementing agencies through a future annual update process.  Those projects will receive conditional approval as part of this approval process.  However, final approval of funds for those projects shall be contingent upon the implementing agency demonstrating the eligibility of each project as required in the Measure M Master Guidelines. 

 

The changes in this annual update include $4,226,964 in deobligation of funds for five previously approved projects, and $17,100,143 in additional programming for eight existing and five new projects.

 

Active Transportation (expenditure line 52)

 

This update includes funding adjustments to ten existing projects and three new projects as follows:

 

Lancaster

 

                     Deobligate $913,478 from MM4501.01 - Avenue I: Sierra Hwy to 10th Street West.  The City requested the funds to be reallocated to other priority project.

 

                     Deobligate $1,890,169 from MM4501.02 - Avenue I: 15th Street West to 30th Street West.  The City requested the funds to be reallocated to other priority project.

 

                     Deobligate $3,192,475 from MM4501.03 - Avenue L: 15th Street West to 40th Street West.  The City requested the funds to be reallocated to other priority project.

 

                     Deobligate $1,499,995 from MM4501.04 - Challenger Way: Avenue I to Avenue L.  The City requested the funds to be reallocated to other priority project.

 

                     Deobligate $26,847 and reprogram remaining funds from FY 19 to FY 21 for MM4501.05 - Sierra Hwy: Avenue J to Avenue L.  The City realigned the MSP funds to match ATP funds for the construction phase.

 

 

Santa Clarita

 

                     Deobligate $672,000 from MM4501.07 - Bicycle Network Connectivity.  The City requested the funds to be reallocated to other priority project.

 

                     Program an additional $24,000 in FY 22 and reprogram $672,000 from FY 21 to FY 22 for MM4501.09 - Santa Clara River Trail Gap Closure.  The City has delayed implementation of the project.

 

                     Deobligate $24,000 and reprogram $672,000 from FY 22 to FY 20 for MM4501.11 - Valencia Industrial Center Bicycle and Pedestrian Improvement Phase I.  The City requested to implement Phase I earlier than originally planned.

 

                     Program $672,000 in FY 21 for MM4501.14 - Valencia Industrial Center Bicycle and Pedestrian Improvement Phase II.  The funds will be used to complete the Plans Specification and Estimates (PS&E), right-of-way (ROW) and construction phases of the project.

 

                     Program $720,000 in FY 23 for MM4501.15 - Railroad Avenue Class I Trail.  The funds will be used to complete the ROW and construction phase of the project, which is also funded by the Metro Call for Projects (#F9513).

 

Los Angeles County

 

                     Reprogram $1,050,000 as follows: $50,000 in FY 20, $300,000 in FY 21, $400,000 for FY 22 and $300,000 for FY 23 for MM4501.12 - Elizabeth Lake Road Bikeways.  The total programmed budget remains unchanged at $1,050,000.

 

                     Program an additional $1,250,000 in FY 23 and reprogram $750,000 as follows: $50,000 in FY 20, $300,000 in FY 21 and $400,000 in FY 22 for MM4501.13 - Lake Los Angeles Pedestrian Plan Implementation Phase 1. The County has delayed implementation of the project.

 

                     Program $1,326,000 in FYs 22 and 23 for MM4501.16 - 30th Street West Active Transportation Improvements.  The project will traverse in both the City of Lancaster and Los Angeles County, but the Los Angeles County will be the lead agency for the project.  The funds will be used to complete the PS&E and ROW phases of the project.

 

Transit Program (expenditure line 64)

 

This update includes funding adjustments to one existing project and one new project as follows:

 

Palmdale

 

                     Reprogram $2,000,000 as follows: $100,000 in FY 20, $1,025,000 in FY 21 and $875,000 in FY 22 for MM4502.01 - Palmdale Transportation Center Transit and Infrastructure Design Project.  The total programmed budget remains unchanged at $2,000,000.

 

Metro/Metrolink

 

                     Program $12,750,000 in FYs 20, 21 and 23 for MM4502.06 - Metrolink Antelope Valley Line.  The funds will be used for the environmental and PS&E phases of the project that Metro and Metrolink have been tasked to lead.

 

Highway Efficiency Program (expenditure line 81)

 

This update includes funding adjustments to two existing projects and one new project as follows:

 

Palmdale

 

                     Reprogram $1,117,074 from FY 20 to FY 21 for MM5504.01 - SR-138 Palmdale Blvd. SR-14 Ramps.  The total programmed budget remains unchanged at $3,351,220.

 

North County Transportation Coalition

 

                     Reprogram $4,700,000 as follows: $2,000,000 in FY 21, $1,350,000 in FY 22 and $1,350,000 in FY 23 for MM5504.02 - SR-14 Capacity Enhancement/ Operational Improvement.  The total programmed budget remains unchanged at $4,700,000.

 

Lancaster

 

                     Program $4,350,143 in FY 22 for MM5504.03 - SR-138 Avenue G Interchange Project.  The funds will be used to complete the ROW and construction phases of the project, which is also funded by the Measure R funds. (#MR330.03)

 

Equity Platform

 

Consistent with Metro’s Equity Platform, the MSP outreach effort recognizes and acknowledges the need to establish comprehensive, multiple forums to meaningfully engage the community to comment on the proposed projects under all Programs. The NCTC JPA along with member agencies and adjacent unincorporated area of Los Angeles County undertook an extensive outreach effort and invited the general public to a series of public workshops and meetings. Metro will continue to work with the Subregion to seek opportunities to reach out to a broader constituency of stakeholders.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

Programming of Measure M MSP funds to the North County Subregion projects will not have any adverse safety impacts on Metro’s employees or patrons.

 

Financial_Impact

FINANCIAL IMPACT

 

In FY 2019-20, $7.79 million is budgeted in Cost Center 0441 (Subsidies to Others) for the Active Transportation Program (Project #474401) and $100,000 is budgeted in Cost Center 0442 (Highway Subsidies) for the Highway Efficiency Program (Project #475504).  Since these are multi-year projects, Cost Centers 0441 and 0442 will be responsible for budgeting the cost in future years.

 

Impact to Budget

 

The source of funds for these projects is Measure M Highway Construction 17% which is not eligible for Metro bus and rail operating and capital expenditures.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

Recommendation supports the following goals of the Metro Vision 2028 Strategic Plan:

 

Goal 1: Provide high-quality mobility options that enable people to spend less time traveling by alleviating the current operational deficiencies and improving mobility along the projects.

 

Goal 4: Transform LA County through regional collaboration by partnering with the Council of Governments and the local jurisdictions to identify the needed improvements and take the lead in development and implementation of their projects.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board could elect not to approve the additional programming of funds for the Measure M MSP projects for the North County Subregion. This is not recommended as the proposed projects were developed by the Subregion in accordance with the Measure M Ordinance, Guidelines and the Administrative Procedures.

 

Next_Steps

NEXT STEPS

 

Metro staff will continue to work with the Subregion to identify and deliver projects.  Program/Project updates will be provided to the Board on an annual basis.

 

Attachments

ATTACHMENTS

 

Attachment A - Active Transportation Project List

Attachment B - Transit Program Project List

Attachment C - Highway Efficiency Program Project List

 

Prepared_by

Prepared by: Fanny Pan, DEO, Countywide Planning & Development, (213) 418-3433

Shawn Atlow, Executive Officer, Countywide Planning & Development, (213) 418-3327

Laurie Lombardi, SEO, Countywide Planning & Development, (213) 418-3251

 

Reviewed_By

Reviewed by: James de la Loza, Chief Planning Officer, (213) 922-2920