File #: 2020-0319   
Type: Informational Report Status: Agenda Ready
File created: 4/27/2020 In control: Construction Committee
On agenda: 5/21/2020 Final action:
Title: CONSIDER amending the Life-of-Project (LOP) budget by $90,000,000 for the Crenshaw/LAX Transit Project (Project) of $2,058,000,000 to $2,148,000,000, consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B).
Sponsors: Construction Committee
Indexes: Alignment, Aviation/LAX Station, Budget, Budgeting, Congestion Mitigation And Air Quality Improvement Program, Construction, Construction management, Contractors, Contracts, Crenshaw/Lax Transit Corridor (Project), Crenshaw/LAX Transit Corridor Project, Division 16, El Segundo, Funding plan, Hawthorne, Informational Report, Inglewood, Light rail transit, Long range planning, Long Range Transportation Plan, Los Angeles International Airport, Measure M, Measure M Multi-Year Subregional Program, Measure R, Measure R and Measure M Unified Cost Management Policy, Metro Crenshaw Line, Metro Exposition Line, Metro Green Line, Metro Rail A Line, Metro Rail C Line, Metro Rail E Line, Metro Rail K Line, Plan, Policy, Policy analysis, Pomona, Professional Services, Project, Project management, Revenue Service, San Gabriel, South Bay Cities subregion, South Bay Subregion Council of Governments, Subregional Equity Program
Attachments: 1. Attachment A - Funding-Expenditure Plan, 2. Attachment B - Measure R and Measure M Unified Cost Management Policy Analysis, 3. Attachment D - SBCCOG letter to Metro CEO re SREP funds for Crenshaw overrun (4-28-20), 4. Attachment C - Projected Breakdown of Cost Allocation for 90 million 5_14_2020 final
Related files: 2020-0195, 2020-0356
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
CONSTRUCTION COMMITTEE
MAY 21, 2020

Subject
SUBJECT: CRENSHAW/LAX TRANSIT PROJECT

Action
ACTION: APPROVE RECOMMENDATION

Heading
RECOMMENDATION

Title
CONSIDER amending the Life-of-Project (LOP) budget by $90,000,000 for the Crenshaw/LAX Transit Project (Project) of $2,058,000,000 to $2,148,000,000, consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B).

Issue
ISSUE

The Substantial Completion date for the Project is currently forecast to be delayed to December 2020 and the revenue service in 2021. As a result, the Project LOP budget needs to be increased, requiring an additional $90,000,000 million beginning in the second half of 2020 for Metro staff and professional service contracts to continue management and oversight of the Project. No additional funding from this LOP increase is designated for the contractor. This represents the first LOP adjustment since the beginning of construction on the Project in 2013.
Background
BACKGROUND

The Crenshaw/LAX Transit Project is a north/south light rail line that serves the cities of Los Angeles, Inglewood, Hawthorne and El Segundo as well as portions of unincorporated Los Angeles County. The alignment extends 8.5 miles, from the Metro E (Expo) line at Crenshaw and Exposition Boulevards to a connection with the Metro Green Line south of the Aviation/LAX Station. The project provides major connections with the Los Angeles International Airport (LAX) as well as links to the C Line (Green), the E Line (Expo) and countywide bus network.
The alignment is comprised of a double-tracked rail line consisting of sections of at-grade in-street, at-grade within railroad right-of-way, aerial, and below-grade guideway sections, eight stations, park and ride facilities at two locations, utilities, landscaping, roadway improvements required by the project and a maintenance & storage facility (Division 16 - Southwestern Yard).
On June 27...

Click here for full text