Meeting_Body
CONSTRUCTION COMMITTEE
JANUARY 21, 2021
Subject
SUBJECT: SOUNDWALL PACKAGE 11 HIGHWAY PROJECT
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
CONSIDER:
A. AMENDING the Life of Project Budget (LOP) Budget for Soundwall Package 11 Highway Project by $13,303,000 from $89,183,000 to $102,486,000, using the fund sources from the soundwall program as summarized in Attachment D consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment E); and
B. AUTHORIZING the Chief Executive Officer to execute individual Contract Modifications within the Board approved Life of Project budget.
Issue
ISSUE
Contract No. C39033C1101-2 Soundwall Package 11 Highway Project (Project) was awarded to Powell Constructors, Inc. in the amount of $ 66,041,760 on October 30, 2017 and Notice to Proceed issued on December 20, 2017. The original schedule for completion of the construction phase of the Project was December 18, 2020 with a subsequent one-year plant establishment period. As of the date of this report, the Project is approximately 60% complete. Project staff have been working diligently to complete the Project within the approved budget; however, the LOP as established prior to Contract notice-to-proceed (NTP) must be increased given certain complexities of the Project as described in this report.
The requested increase to the LOP addresses all current and future direct and indirect cost impacts and will provide enough funding to complete the Project.
BACKGROUND
The Project is being performed under a Design/Bid/Build contract that is administered by Metro on behalf of Caltrans. The Project is located entirely within Caltrans right of way and consists of construction of soundwalls on Route 170 from Route 101/Route 170 interchange to the Sherman Way Overcrossing, and on Route 405 from north of Saticoy Street Undercrossing to Roscoe Boulevard Undercrossing. The cons...
Click here for full text