Meeting_Body
SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE
OCTOBER 15, 2015
Subject/Action
SUBJECT: LIFE-OF-PROJECT FOR REDUCED RISK OF AN EVENT TO UNION STATION GATEWAY COMPLEX
ACTION: AUTHORIZATION FOR LIFE OF PROJECT BUDGET
Heading
RECOMMENDATION
Title
CONSIDER:
A. APPROVING Life-Of-Project budget for the capital project, Reduced Risk of an Event to Union Station Gateway Complex in the amount of $6,985,096; and
B. AMENDING System Security and Law Enforcement FY16 budget in the amount of $6,885,096.
Issue
ISSUE
Staff is requesting an approval of Life-Of-Project for the capital project, Reduced Risk of an Event to Union Station Gateway Complex. This approval will authorize staff to proceed with the hardening of the Union Station Gateway Complex.
Discussion
DISCUSSION
In FY15, Metro staff submitted an Investment Justification Application under FY14 Department of Homeland Security (DHS) Transit Security Grant Program (TSGP) to secure funding to harden Union Station Gateway Complex. DHS awarded Metro $6,285,096 to complete the project. The hardening of the Union Station Gateway Complex will encompass the following:
A. Emergency Notification System and Emergency Operations Center
An emergency notification system is critical to Union Station Gateway Complex to assist patrons in announcing and directing evacuation routes during an emergency. The emergency notification system will provide both visual and audio emergency announcements for the patrons.
The Union Station Gateway Complex consists of multiple agencies that provide transportation and emergency services. In an event of an emergency, a centralized location for coordination and response is critical to mitigating the risk. Therefore, the installation of an emergency operations center in Union Station Gateway Complex is essential to address this need.
B. Mobile Data Terminal
The need for sharing video intelligence to appropriate transit agencies and first responders during an emergency is critical. The mobile data terminal is a platform that allows the sharing of closed-circuit television via smartphone and tablets for authorized users. The ability to obtain mobile video intelligence instantly, and shared among authorized agencies will provide situational awareness and help coordinate response efforts during an emergency.
C. Harden Metro Gateway Headquarters
The hardening of Metro Gateway Headquarters is critical to the safety of the public visiting Metro Gateway Headquarters and employees that support the operations of Metro transit system. To protect the safety of the public and employees, the hardening of Gateway Headquarter will involve the following:
• Install additional high definition closed-circuit televisions in parking structures and building.
• Install emergency call boxes on each floor of the parking structure.
• Enhance access control to further secure the Gateway Headquarters.
Staff is anticipating the completion of this project in August 2016 (Attachment A: Project Summary Schedule).
Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT
This capital project will provide a positive safety impact for Metro employees, patrons, and visitors by enhancing the safety and security against potential terrorist incidents as well as provide higher quality situational awareness.
Financial_Impact
FINANCIAL IMPACT
Staff is requesting to amend the FY16 budget in the amount of $6,885,096 for this capital project, in cost center 2610 System Security and Law Enforcement. Since this is a multi-year project, the executive officer of System Security and Law Enforcement is responsible for budgeting in future years.
Impact to Budget
The DHS grant funds $6,285,096 of this project. The $700,000 balance of the project cost is funded by Transit Development Act Article 4, which is eligible for bus and rail operating and capital improvements.
Alternatives_Considered
ALTERNATIVES CONSIDERED
An option considered would be not to approve the funding from Department of Homeland Security Grant Program. This alternative is not recommended because this is a critical Security program to ensure the safety of the patrons and Metro employees by hardening the Union Station Gateway Complex.
Next_Steps
NEXT STEPS
Upon approval of recommendation, Metro staff will set up the LOP and the FY16 annual budget for the capital project and begin work.
Attachments
ATTACHMENTS
Attachment A - Project Summary Schedule
Attachment B - Financial Forecast
Prepared_by
Prepared by: Duane Martin, DEO, Project Management, (213) 922-7460